Vertical Sidewall Applications & Installation - Majestic DV360 Homeowner's Installation And Operating Manual

Table of Contents

Advertisement

Vermont Castings Majestic Products DV360/580 Series
Rear Wall Vent Installations
Step 1
Locate and cut the vent opening in the wall.
For combustible walls first frame in opening. (Fig. 21)
Combustible Walls: Cut a 10³⁄₈"H x 9³⁄₈" W (265mm x
240mm) hole through the exterior wall and frame as
shown. (Fig. 21)
Noncombustible Walls: Hole opening should be 7¹⁄₂"
(191mm) diameter.
Zero clearance sleeve is only required for
combustible walls.
Step 2
Measure wall thickness and cut zero clearance sleeve
parts to proper length (Maximum 12" / 305mm). As-
semble sleeve to its maximum opening (10³⁄₈" x 9³ ₈")
and attach to firestop assembly. (Fig. 22)
Step 3
Measure the horizontal length requirement for the
f i r e - p a r t s . c o m
venting including a 2" (51mm) overlap, i.e. from the
elbow to the outside wall face plus 2" (51mm). (Fig. 20)
Vent Opening for Combustible Wall
9³⁄₈"
(240 mm)
10³⁄₈"
(265 mm)
Fireplace Hearth
Opening for Noncombustible Wall
7¹⁄₂" Dia.
(190 mm)
Fireplace Hearth
Fig. 21 Locate vent opening on wall.
Adjustable Zero
Clearance Sleeve
#8 Screws (2)
Adjustable Zero Clearance Sleeve
Fig. 22 Adjustable zero clearance sleeve.
14
Framing
Detail
Rnd.
VO584-100
Max. Length 12"
(305mm)
#8 Screws (2)
#8 Screws
(2)
Firestop
ZCS101
Step 4
Install the 4" (102mm) vent to the appliance collar and
secure with 3 sheet metal screws. Install the 7"
(178mm) vent pipe to the appliance collar and secure
with 3 sheet metal screws. It is not necessary to seal
this connection. If a 45° elbow is being used attach the
elbow to the appliance in the same manner then attach
the venting to the elbow.
It is critical that there is no downward
slope away from the appliance when
connecting the vent or elbow.
Step 5
Guide the venting through the vent hole as you place
the appliance in its installed position. Guide the 4"
(102mm) and 7" (178mm) collar of the vent termination
into the outer ends of the venting. Do not force the
termination. If the vent pipes do not align with the
termination, remove and realign the venting at the
appliance flue collars. (Fig. 23) Attach the termination
to the wall as outlined in the instruction sheet supplied
with the termination.
Finished
Wall
Fig. 23 Side view of final unit location.
Vertical Sidewall Applications
Since it is very important that the venting system
maintain its balance between the combustion air
intake and the flue gas exhaust, certain limitations
as to vent configurations apply and must be strictly
adhered to.
The Vent Graph, showing the relationship between
vertical and horizontal side wall venting, will help to
determine the various dimensions allowable.
Minimum clearance between vent pipes and com-
bustible materials is one inch (25mm) on top,
bottom and sides unless otherwise noted.
Vent
Termination
FP1005
20002261