Setting Up Rack To Mount Hardware - Nortel Sun Fire V210 (RoHS) Installation And Commissioning Manual

Multimedia communication server 2-server sun fire v210
Table of Contents

Advertisement

Copyright © Nortel Networks Limited 2006

Setting up rack to mount hardware

Procedure 1 Setting up rack to mount hardware
At the rack,
1
MCS 2-server Sun Fire V210 (RoHS) Solaris Installation and Commissioning Guide
Make sure you have
Business Policy Switch 2000 (BPS 2000) or Layer-2 switch
vendor documentation for configuring your Layer-2 switch
one (1) additional cat-5 ethernet cable to connect the MRV LX
terminal server to the layer-2 switch
a pc for the System Management Console, and access to the
network
WARNING
Static electricity could be harmful to the servers.
Mount all equipment. Refer to the following diagram that displays
the mounting for the rack.
Mount Layer-2 switch.
Mount the MRV LX terminal server.
Mount Sun Fire V210s.
— Database/Management/Accounting server
— Application server
(optional equipment) Mount conference server. Refer to the
Media Application Server documentation for more
information.
(optional equipment) Mount gateway. Refer to
customer-specific gateway installation documentation.
Note: All MCS equipment is 19-inch rack mountable.
27
ATTENTION

Advertisement

Table of Contents
loading

This manual is also suitable for:

Nn42020-310

Table of Contents