Powerware 9330 Installation & Operation Manual page 34

Ibm 9910 ups 20 kva
Table of Contents

Advertisement

4.
Loosen screws securing Distribution Housing to Options cabinet. Lift
Distribution Housing up and remove from Options cabinet.
5.
Remove three bolts, (1) in Figure 2---4, securing the rear shipping bracket (3)
to the cabinet and three bolts (2) securing the bracket to the pallet. Remove
the rear shipping bracket. If installing cabinet permanently, retain shipping
brackets and securing hardware for later use.
6.
Remove three bolts, (1) in Figure 2---3, securing front shipping bracket (3) to
the pallet. Do not remove bolts (2) securing the bracket to the cabinet.
7.
Remove three bolts, (4) in Figure 2---4, securing removable skid (5) and
remove skid.
NOTE: In the following step the pallet will tilt and act as a ramp once the cabinet is
rolled beyond the the center of the pallet. Make sure to restrain the cabinet
as it continues to roll down the pallet/ramp. The front shipping bracket will
act as a brake to assist restraining the cabinet.
WARNING:
Do not stand directly behind the pallet while unloading the cabinet If
unloading instructions are not closely followed, the cabinet may cause
serious injury.
8.
Slowly roll the cabinet toward the rear of the pallet. Once the pallet tilts,
continue rolling the cabinet down the pallet until the cabinet is clear of the
pallet.
9.
Remove three bolts, (2) in Figure 2---3, securing front shipping bracket to the
cabinet.
10.
If installing cabinet permanently, retain shipping brackets and hardware;
otherwise, discard or recycle the pallet and brackets in a responsible manner.
11.
Reinstall Distribution Housing over screws on rear of Options cabinet. Tighten
screws to secure Distribution Housing to Options cabinet.
12.
Roll cabinet to final installation location.
13.
If permanently mounting the system, proceed to step 17; otherwise, proceed to
step 14.
15.
Secure the Options cabinet in position by lowering the leveling feet, until
cabinet is not resting on the casters and the cabinet is level.
16.
If installing Battery cabinets, proceed to paragraph 2.3 for Battery cabinet
installation and then proceed to paragraph 2.4 for Options cabinet installation;
otherwise, proceed to paragraph 2.4.
17.
Using retained hardware, reinstall shipping brackets previously removed to
front and rear of Options cabinet with the angle facing outward (see Figures
2---3 and 2---4).
18.
Secure Options cabinet to floor with contractor supplied hardware.
19.
If installing Battery cabinets, proceed to paragraph 2.3 for Battery cabinet
installation and then proceed to paragraph 2.4 for Options cabinet installation;
otherwise, proceed to paragraph 2.4.
2--8
Powerware 9330 (IBM 9910 20 kVA) Installation and Operation
164201491 REV. B 013004