1.
Carefully inspect the outer packaging for evidence of damage during transit.
CAUTION:
Do not install a damaged cabinet. Report any damage to the carrier and
contact your local sales or service office immediately.
2.
Use a forklift or other material handling equipment to move the cabinets to a
convenient unpacking area. Insert the forklift jacks between the pallet
supports on the bottom of the unit.
CAUTION:
Do not tilt cabinets more than 10 degrees from vertical.
3.
Set each pallet on a firm, level surface, allowing a minimum clearance of
3 m (10 ft) on each side for removing the cabinets from the pallets.
4.
Remove the protective covering from the cabinets.
5.
Remove the packing material, and discard or recycle them in a responsible
manner.
6.
After removing the protective covering, inspect the contents for any evidence
of physical damage, and compare each item with the Bill of Lading. If damage
has occurred or shortages are evident, contact the Powerware, Inc. Customer
Service Department immediately to determine the extent of the damage and its
impact upon further installation.
NOTE: While awaiting installation, protect the unpacked UPS cabinets from
moisture, dust, and other harmful contaminants. Failure to store and
protect the UPS properly may invalidate the warranty.
Powerware 9330 (IBM 9910 20 kVA) Installation and Operation
164201491 REV. B 013004
1--5