INDOOR UNIT INSTALLATION
2. Make the power connection wire go
through the cable-cross hole at the back
of indoor unit and then pull it out from
the front side.
3. Remove the wire clip; connect the power connection wire to the wiring terminal
according to the color; tighten the screw and then fix the power connection wire
with wire clip.After finishing wiring, clamp the grounding wire (yellow-green wire)
into the wire-crossing groove as shown in the following figure, in order to avoid
pressing the wire when closing the electric box cover.
/-
...........................
_t
........
-.\
white
black
red
I,g teen
i
(blue)
[
I(brown) I_/ell°w:
!:__4__t:_4
ooo,,
Outdoor unit connection
,
4.Put wiring cover back and then tighten the screw
5.Close the panel.
Note:
• All wires of indoor unit and outdoor unit should be connected by a professional.
• If the length of power connection wire is insufficient, please contact the supplier
for a new one. Avoid extending the wire by yourself.
• For the air conditioner with plug, the plug should be reachable after finishing
installation.
• For the air conditioner without plug, an air switch must be installed in the line.
The air switch should be all-pole parting and the contact parting distance should
be more than 2/17 in (3mm).