6.2.10 Completing The Verification; Installation - GE Hydran 201 i Instruction Manual

Hide thumbs Also See for Hydran 201 i:
Table of Contents

Advertisement

22. When the testing is completed, repeat the steps 2 to 13 above but restore the original
communication settings to the following:
• Comm Channel = Supervisory Link
• Default Channel = Supervisory Link
• Gas Monitor ID = Initial value noted in the step 11 above
23. Disconnect the RS-232 link cable.

6.2.10 Completing the Verification

This completes the incoming verification of the Hydran 201Ti.
1.
Disconnect the H201Ti from the power outlet.
2.
If a Hydran 201Ci-C is available, perform the procedure in Section 7.2 on page 7-2.
3.
If a Hydran 201Ci-1 is available, perform the procedure in Section 8.2 on page 8-2.
4.
If no H201Ci Controller is available, remove the power and computer cables from the
H201Ti.
5.
Close the H201Ti cover.
6.
Store the H201Ti in its box, ready for installation.
7.
If the H201Ti is not installed immediately, refer to Section 6.1.4 on page 6-5.
6.3

INSTALLATION

This Section explains how to install the Hydran 201Ti, the brass adaptor and the
Hydran 201 sensor; it refers to Figure 6-2 on page 6-18.
Read all the warnings and recommendations in Section 5.1 on
WARNING
CAUTION
page 5-1 before proceeding with the installation.
Note: It is strongly recommended that the operation of all H201Ti's and H201Ci
Controllers be verified before installation of the equipment in the field. Verification also
allows the user to become familiar with the Hydran 201i System.