Installation sequence
Mounting the boiler and making connections
Filling the trap with water
Balanced flue connection
Do not carry out commissioning until
the following conditions are met:
■ Free passage through the flue gas
pipes.
■ Flue system with positive pressure is
gas-tight.
■ Apertures for ensuring sufficient com-
bustion air supply are open and cannot
be closed off.
■ Applicable regulations on installing
and commissioning flue systems have
been followed.
16
(cont.)
Pour at least 0.3 l of water into the flue
outlet.
!
Please note
During commissioning, flue gas
may escape from the condensate
drain.
Always fill the trap with water
before commissioning.
Connect the balanced flue.
Flue system installation instruc-
tions
Danger
Leaking or blocked flue systems
or an insufficient supply of com-
bustion air cause life threatening
poisoning due to carbon monox-
ide in the flue gas.
Ensure the flue system functions
correctly. Apertures for combus-
tion air supply must not be able to
be closed off.