Ignition Electrode And Lead Replacement; Main Burner And Main Burner Injector Replacement - IDEAL Henrad WH LX 30 FF Installation And Servicing Manual

Wall hung, fanned flued, gas fired boiler
Table of Contents

Advertisement

59 IGNITION ELECTRODE AND LEAD REPLACEMENT

1. Refer to Frame 54.
2. Remove the burner and air box assembly. Refer to Frame 49.
3. Remove the electrode retaining nut.
4. Remove the pilot shield.
5. Remove the ignition electrode and integral lead.
6. Refit the new electrode and lead in reverse order.
Ensure that the pilot shield is replaced.
7. Check the spark gap. Refer to Frame 58.
8. Refit the burner.
9. Replace the boiler casing.
10. Check the pilot ignition.

60 MAIN BURNER AND MAIN BURNER INJECTOR REPLACEMENT

1. Refer to Frame 54.
2. Remove the screw retaining the front burner support
strap to the combustion chamber.
3. Remove the M5 pozi screw, situated at the left hand
bottom rear of the burner. Pull the burner downward to
disengage the retention tab and remove the burner.
4. At this stage the main burner injector can be removed,
checked, cleaned or replaced as required. Ensure that
an approved jointing compound is used sparingly.
5. Fit the new burner, ensuring that the retention tab is
correctly located in the air box slot.
6. Refit the M5 retaining screw.
7. Refit the boiler casing.
8. Check the burner for cross-lighting and flame stability.
61 GAS CONTROL VALVE REPLACEMENT
Note. Also refer to Frame 69 of 'Exploded Views' for
illustration of the procedure detailed below.
1. Refer to Frame 54.
2. Remove the burner and air box assembly. Refer to
Frame 49.
3. Remove the control box fixing screw. Pull the box
forward and downward to disengage.
4. Remove the gas control valve electrical connection.
5. Disconnect and remove the gas union from the gas
control valve.
6. Whilst supporting the gas control valve, remove the 2
screws retaining the manifold to the back panel.
30
SERVICING
7. Remove the gas control / manifold assembly.
8. Remove the 4 screws retaining the manifold to the gas
control valve, and fit the manifold to the new gas control
valve. Ensure that the new control is fitted the correct
way round (an arrow engraved on back indicates the
direction of flow).
Note. Remove the gas cock stub and refit into the new
gas control valve. Use an approved jointing compound
on the pipe stub.
9. Re-assemble in reverse order.
10. Replace the boiler casing.
11. Check the gas valve operation.
Henrad WH LX
FF, FF
-
Installation

Advertisement

Table of Contents
loading

Table of Contents