Figure 4.17: Stainless Steel Vacuum Breaker / Supply Box
Figure 4.18: Poly Vacuum Breaker / Supply Box

4.11 Control Function Test

The machine should be cleaned after the installation is complete. A function test should then be
executed on the unloaded machine as follows:
1. Check the proper supply for such characteristics as correct voltage, phase, and cycles to be
certain they are correct for the machine.