Chute Up Switch Installation; Control Function Test - B&C Technologies SI Series Installation And Operation Manual

Si series;
Table of Contents

Advertisement

Figure 5.8: External Chemical Supply Terminal Block Detail
inserted and tightened.
Connect Hydraulic rams
Temporarily install Chute Up Switch to operated the chute
Apply electrical and air to machine
Operate the chute, using the maintenance switch to make sure the safety locks properly en-
gage freely
Use the pendant to lower the chute, CHUTE ENABLE and LOAD, ensure safety locks disen-
gage freely
Adjust safety locks until chute operates properly
When properly aligned remove Chute Up Switch and weld in place
Re-install Chute Up Switch

5.12.1 Chute Up Switch Installation

NOTE: Chute must me in the full up position Install mounting bracket and adjust switch so that
half the length of the plunger is depressed. Refer to figure 5.10 on page 30.

5.13 Control Function Test

The machine should be cleaned after the installation is complete. A function test should then be
executed on the unloaded machine as follows: