Mounting Bolt Installation - B&C Technologies SI Series Installation And Operation Manual

Si series;
Table of Contents

Advertisement

For a successful installation, a smooth level surface, so that the entire base of the machine is sup-
ported and rests on the mounting surface, is absolutely requried.
Note: Do not support the machine on only four points.
Note: Freestanding washer-extractors do not require anchoring bolts unless specified by state
or local codes. However it is always recommended that the machines be anchored.
Special care must be taken when machines are installed on an upper floor. Make sure that the floors
are designed to carry the static and dynamic loads of the machines. Further vibrations should be
taken into consideration so that the machine does not create vibrations in the building. Static and
dynamic loads on the floor or foundation are shown in the figure 5.2 on page 18. This table can
be used as reference when designing floors and foundations.
Static floor load
kN
SI-110
15
SI-110 TILT
17
SI-135
22.3
SI-135 TILT
24.9
SI-200
26.8
SI-200 TILT
30.25
SI-275
47.7
SI-275 TILT
51.3

5.4.1 Mounting Bolt Installation

All B&C washer-extractors should be secured by the use of machinery anchor bolts. High strength
machinery anchors should be embedded in 3500 psi (24000 N/m2) reinforced concrete. For de-
tailed information regarding the machine anchor bolt, see the instructions included with the an-
chor bolts themselves. The information provided is just an example. Ensure that the concrete is
fully cured before proceeding.
Place the machine adjacent to the foundation. Do not attempt to move it by pushing on the sides.
1. Remove the wood skid by unscrewing the carriage bolts holding it to the bottom frame of
the machine.
2. Carefully place the machine over the anchor bolts. Raise and level it 1/2 inch above the floor
on four points, using spacers that can be removed.
3. Fill the spaces between the machine base and floor with machinery grout. Grout completely
under all frame members. Remove front panel and rear panel to gain access to all frame
members. Force grout under the machine base until all voids are filled.
Table 5.2: Floor Load Data
Static pressure
Dynamic floor load
lbs
kN/m2
lbs-ft2
3300
5.7
117
3900
6.5
138.5
4900
7.4
152
5600
8.3
173.9
5900
7.13
149
2.45
6800
7.13
149
2.45
10500
11.96
248
4.09
11300
13.05
267
4.09
Max dynamic load
kN
lbs
kN
1.5
330
1.5
1.5
330
1.5
1.5
330
1.5
1.5
330
1.5
540
2.45
540
2.45
900
4.09
900
4.09
18
Dynamic pressure
lbs
kN/m2
lbs-ft2
330
0.57
11.7
330
0.57
11.7
330
0.5
10.25
330
0.5
10.25
540
0.88
18.3
540
0.88
18.3
900
1.04
21.3
900
1.04
21.3