The built-in copper coil provides copious amounts of The complete system tank hot water. The CTC EcoZenith i250 also has a so- The CTC EcoZenith i250 is a complete system tank called summer-time basement heating function and a which meets your home’s heating and hot water...
• Following installation, the unit must be inspected, functional checks performed and the customer informed. The points below should be checked off. Pipe installation CTC EcoZenith i250 filled, positioned and adjusted in the correct manner according to the instructions. CTC EcoZenith i250 positioned so that it can be serviced.
See the chapter on Operation and maintenance. If these instructions are not followed when installing, operating and maintaining the system, Enertech’s commitment under the applicable warranty terms is not binding CTC EcoZenith i250...
Installer/Settings/Radiator system menu. Recommended values are: Floor heating only Inclination 35 Low temperature system (well insulated houses) Inclination 40 Normal temperature system (factory setting) Inclination 50 High temperature system (older houses, small radiators, poorly insulated) Inclination 60 CTC EcoZenith i250...
Page 9
50 °C when the outdoor temperature is –15 °C (if adjustment is set to 0). If the adjustment is set to +5, the temperature will be 55 °C instead. The curve is increased by 5 °C at all temperatures, i.e. it is parallel displaced by 5 °C. CTC EcoZenith i250...
Page 10
Installer/Settings/Radiator system menu. When the heat is switched off in this way, the radiator pump stops and the mixing valve is shut down. The heating starts up automatically when it is required again. Outside Temperature Heating off, out CTC EcoZenith i250...
General Information 2. Technical data Table 400V 3N~ Electrical Data CTC EcoZenith i250 H CTC EcoZenith i250 L Electrical data 400V 3N~ Rated power 15.04 15.04 Immersion heater (steps of 0,3 kW) 0 - 15.0 Max immersion heater output @ fuse size 16 / 20 / 25 A...
Page 12
General Information 2.2 Table 230 V 1N~ CTC EcoZenith i250 H CTC EcoZenith i250 L Electrical Data Electrical data 230V 1N~ Rated power 12,04 12,04 Immersion heater (steps: 3, 5, 7, 9, 12 kW) 0-12 Max immersion heater output @ fuse size 16 / 20 / 25 A...
General Information 4. CTC EcoZenith i250 design The picture below shows the basic construction of CTC EcoZenith i250. If a heat pump is connected, the energy in the air or bedrock/ground is drawn up by the cooling system. The compressor then increases the temperature to a usable level.
Boiler low kW Delay mixing valve Main fuse A Input voltage 3x400 V Tariff EL Upper tank Factory User (set) value value Stop temp HP ºC Max. Start/stop diff ºC Max. time upper tank Max. time lower tank CTC EcoZenith i250...
Room temperature settings Cooling Factory values Common heating/cooling Room temp. The CTC EcoZenith i250 is delivered with set factory Weekly schedule Condense pipe secured values which are suitable for a standard house with Heating circuit 1 Room temp. cooling a standard radiator system.
Software HP PCB: 20120125 Software display PCB: 20120205 T ºC Software display PCB: 20120205 Software HP PCB: 20120125 Software HP PCB: 20120125 Software display PCB: 20120205 Software HP PCB: 20120125 Installer settings menu Installer CTC EcoZenith i250 Room1 Prim1 Return Room2 Prim2...
Page 18
Installer settings menu Current L1/L2/L3 0.0 0.0 0.0 Electric power kW 0.0 0.0 0.0 Heating circuit 2 Current L1/L2/L3 0.0 0.0 0.0 Installer Operation data heating CTC EcoZenith i250 T ºC Operation data heating Room1 Prim1 Return Room2 Prim2 T ºC...
Page 19
DHW Control current sensors er L3B Re-installation er A13 program Day by day 06-09 18-21 07-09 00-00 Svenska Nederlands English Deutsch sday 06-09 00-00 06-09 00-00 06-09 00-00 10-12 00-00 Installer Suomi Française Dansk Norsk 10-12 00-00 CTC EcoZenith i250...
Page 20
Operation data heating Heating circuit 2 T ºC Heat pump Cooling Service Room1 Prim1 Return Room2 Prim2 Function test Alarm log Factory settings coded Quick start compressor. Software update, USB Write log to USB Control current sensors Re-installation CTC EcoZenith i250...
Page 21
Control current sensors Boiler lower max kW -installation Re-installation Delay mixing valve Main fuse A Input voltage 3x400 V Upper tank Stop temp HP °C Start/stop diff upper ºC Max time upper tank Max time lower tank CTC EcoZenith i250...
Page 22
Factory settings coded Valves Valves Quick start compressor. Quick start compressor. Electric heater Electric heater Software update, USB Software update, USB Write log to USB Write log to USB Control current sensors Control current sensors Re-installation Re-installation CTC EcoZenith i250...
The heating system’s structure can be This displays the current outdoor temperature. adjusted/modified using this option. Home Service The Home button takes you back to the Start Advanced settings are configured by the menu. appropriate technical person. Installer settings menu Installer CTC EcoZenith i250...
The Compressor Permitted room sensor can temporarily be deselected during the Min outdoor temp °C Brine pump on 10 days firing process. The EcoZenith i250 then provides heating 22,2 ºC 21,2 ºC 58 ºC -5 ºC Tariff HP to the radiators using the set heating curve.
-5 °C is simulated so that the house tuned. does not get cold. The product's alarm is triggered. If a fault occurs with a room sensor, the EcoZenith i250 automatically switches to operating according to the set curve. The product's alarm is triggered.
Primary flow °C 42 (43) Stored oper data Return flow °C You set the values for this option which apply to the Radiator pump CTC EcoZenith i250’s normal operation. There are three Mixing valve Open Heating circuit 1 Weekly schedule Weekly program...
0.0 0.0 0.0 Heating circuit 2 Current L1/L2/L3 0.0 0.0 0.0 Operation data heating T ºC settings menu staller Room1 Prim1 Return Room2 Prim2 anguage Settings Define system Service ware display PCB: 20120205 ware HP PCB: 20120125 CTC EcoZenith i250...
Installer settings menu temperature. Installer Operation data system Return radiators The return temperature of the radiator water returning to EcoZenith is also shown above the CTC EcoZenith i250 (34°C). This value will vary during operation according to Time/Language Settings Define system Service the parameters set, the radiator system’s capacity and...
This menu displays current temperatures and the Tank lower °C 42 (45) Primary flow °C 42 (43) Stored oper data operational data for your EcoZenith i250. The first figure Return flow °C is the actual operational value, with the value in brackets Radiator pump Mixing valve Open being the setpoint which EcoZenith is trying to achieve.
Remote control w °C 1 and 2, respectively. Communication ware display PCB: 20120205 Save settings Open The yellow curve is the CTC EcoZenith i250 return ware HP PCB: 20120125 Load settings ng valve Load factory settings wer kW 0.0 0.0 0.0 temperature.
Time/Language includes time and language settings for Operation time /24 h:m 00:00 t reduction heat circ. 06 - -- -- - 21 your CTC EcoZenith i250. 10 - 12 20 - 23 ogram Day by day Total operation time h:...
Your property’s heating installation. The value set is the outgoing flow temperature to radiators when the outdoor temperature is -15 °C. After this default setting, fine adjustment takes place in the “Room temperature” menu. CTC EcoZenith i250...
After installation is complete, you can choose to run the brine pump constantly for 10 days to remove air from the system. Upper tank Stop temp HP °C Start/stop diff upper ºC Max time upper tank CTC EcoZenith i250 Max time lower tank...
50 (30 to 60) Boiler upper °C Temperature when the immersion heater kicks in Boiler upper add °C and helps EcoZenith i250 to produce domestic hot Boiler upper extra DHW °C Boiler upper max kW water when there is great demand. A low setting is Boiler lower °C...
Max.time lower tank, mins 40 (10 to 120) This is the maximum time spent by the heat pump charging the lower tank if it is needed in the upper tank. CTC EcoZenith i250...
Boiler lower °C Delay mixing valve Boiler lower max kW Main fuse A Delay mixing valve Input voltage 3x400 V Main fuse A Input voltage 3x400 V Upper tank Upper tank CTC EcoZenith i250 Stop temp HP °C Start/stop diff upper ºC...
Boiler upper extra DHW °C Rad pump2 Boiler upper max kW Activate GSM? LED room sensor Boiler lower °C Level of signal ------- Boiler lower max kW CTC EcoZenith i250 Delay mixing valve Phone number 1 46704130901 Main fuse A Phone number 2 ---------------...
In the event of doubt, contact an expert surveyor for an assessment. Room temperature cooling 25 (10 to 30) This is used to set the desired room temperature for cooling. Operation data system NOTE: See CTC EcoComfort manual for more information. CTC EcoZenith i250...
The fan or brine Heating Cable 4-way valve(Y11) pump and charge pump are also operating so that the compressor is not going to trigger its pressure switches. Test valves Save settings 3-way valve Down Save settings? CTC EcoZenith i250...
Page 42
Several minutes All three currents (L1, L2 and L3) will appear in the may pass before the display current operational data when EcoZenith i250 has communicates clearly after restart. identified the current transformers’ relevant phases. When activating the function “Control current sensors”...
Air must be supplied to the closed system. Shut-down The CTC EcoZenith i250 is shut down using the operating switch. If there is a risk of the water freezing, all the water should be drained from the heat pump and the radiator system (see drainage above).
General Information 10. Troubleshooting/measures The CTC EcoZenith i250 is designed to provide reliable operation and high levels of comfort, and to have a long service life. Various tips are given below which may be helpful and guide you in the event of an operational malfunction.
Page 45
Touch the entire radiator surface. Bleed the radiators. The CTC EcoZenith i250's economical operation requires that the radiator system functions well, if you are to make good savings.
Page 46
In some cases, unusual noises may be produced by the house's pipe system and the CTC EcoZenith i250 due to the jolts which occur when the flow is quickly interrupted. There is no fault with the product, but the noise may occur when older model outlets are used.
The compressor is set to be shut down, e.g. before drilling or digging has been carried out for the collector loops. The product comes with the compressor shut off. This option is selected under the Installer/Settings/Heat pump menu. CTC EcoZenith i250...
Collectors which are too long can also be a cause. Check also that the brine pump is set to speed 3. Press reset and check whether the alarm recurs. Also check the brine filter that has been installed. If the fault recurs, contact your installer. CTC EcoZenith i250...
Page 49
This message appears in the event of a phase failure. Call in a specialist to check the cause. Compressor type? This message appears if there is no information about the compressor type. Heat pump alarm This message appears if the heat pump is in alarm mode. CTC EcoZenith i250...
• Forklift • Lifting eye that has been fitted to the lifting sleeve on top of the EcoZenith i250. An extra sleeve can be found in the middle, under the insulation. • Lifting band around the pallet. NB: Can only be used with the packaging on.
When filling the system, the mixing valve (Y1) must be wide open. Pull out the knob on the valve and turn it anticlockwise as far as you can. Do not forget to push in the valve’s knob in automated mode. CTC EcoZenith i250...
Start with the heat requirement in kW (e.g. 15 kW), then move vertically to the selected ∆t (e.g. 10°C). Then move horizontally to the line for the EcoZenith i250 mixing valve = line 6.3 DN20. The reading for the pressure drop is taken from the scale directly below (4 kPa).
Installation 12.2 Schematic diagram This shows the main connection between the CTC EcoZenith i250 and the property’s radiator and hot water system. Different installations and systems may look different, such as a one- or two-pipe system, which means that the finished installation may be different.
Page 54
Observe the building regulations of the Swedish National Board of Housing, Building and Planning (Boverket) and the standard SS-EN 1717. Manometer system pressure (95) Fit the manometer on the expansion pipe or radiator return pipe. CTC EcoZenith i250...
Page 55
The CTC EcoZenith i250 is best connected to a closed expansion vessel. The CTC EcoZenith i250 is designed to be fitted to an 18 l closed expansion vessel. The expansion vessel is either fitted in the area under the tank or on top of the product (see pictures).
The charge pump for the heat pumps is factory-installed in the CTC EcoZenith i250L. The CTC EcoZenith i250 L has pipes at the rear right edge for connection of the heat pump.
Page 57
Installation Pipe connection for CTC EcoZenith i250 H (The picture shows the back of the product) Incoming (heated water) from heat pump Outgoing (cold water) to heat pump Preassembled charge pump on CTC EcoZenith i250L installed on 250 H (behind the diverting valves).
Installation 12.4 DHW system You can connect a DHW circulation system. You can see this kind of connection in the figure below. DHW pump (43) BV CTC EcoZenith i250...
Connecting external systems can seriously affect the EcoZenith’s operation and performance and can therefore produce undesirable effects if the system is not installed correctly. If you are unsure how to make the connection, contact CTC for suggestions on how to install the system. CTC EcoZenith i250...
The boiler is internally connected by the factory and set for a 5.5 + 6.0 kW power output. Depending on the country in which CTC EcoZenith i250 is to be installed, it is available with a 400 V or 230 V electrical connection.
The factory-installed charge pump for heat pumps is connected internally in the CTC EcoZenith i250 L. Charge pump Molex switch The charge pump is connected to CTC EcoZenith i250 H in the pre- assembled connector (Molex and PWM) located under the electrical cabinet. When working on the heat pump...
Installation 13.4.2 Heat pump power supply 400 V 3N~ The heat pump must be supplied with power from CTC EcoZenith i250 using the provided black connector located in the bottom of the electrical cabinet. (NB: no supply to CTC EcoZenith i250) The minimum group fuse size is specified in “Technical data”.
Apply contact paste to the end part of the sensor between the sensor and the pipe if good contact is otherwise difficult to obtain. • Important! Insulate the sensor using pipe insulation. • Connect the cables to the EcoZenith’s terminal board. CTC EcoZenith i250...
This means that the current sensors, along with the electronics, prevent more power being supplied than the main fuses can tolerate. Use at least 0.5 mm cable. Connection block From electricity meter To boiler Low current Current Fuse panel sensor CTC EcoZenith i250...
10 A 1.3 A Power 1.2 kW 2.3 kW 0.6 kW 2.3 kW 0.3 kW 1x230 V Switch Phase Current 8.7 A 8.7 A 8.7 A 13 A Power 2.0 kW 2.0 kW 2.0 kW 3.0 kW CTC EcoZenith i250...
Installation 14. Connecting –Increased immersion heater output 15 kW to 18 kW. CTC EcoZenith i250 3x400 V can be reconnected to a 18 kW immersion heater NB: Installation must be carried out by a qualified electrician. Connecting 1. Begin by disconnecting the power to the product.
Page 69
Then check that the switch is firmly in position on the DIN rail. 5. Mount the black wires in the free spaces on the electric heater. NB: Only for angled flat pins with black end cable sleeves. CTC EcoZenith i250...
Installation 15. First start Symbol for backup heating When the CTC EcoZenith i250 is delivered, the heat pump is blocked to avoid it thermostat: being started unintentionally. EcoZenith I250 can be installed and started before the bedrock/ground source or air/water heat pump is put into operation.
Page 77
Specify the adjustment for radiator system 2. If the primary flow sensor for radiator system 2 is installed, repeat steps 7 to 9 for radiator system Current sensors identified. The CTC EcoZenith i250 then starts and the start menu appears.
Försäkran om överensstämmelse Déclaration de conformité Declaration of conformity Konformitätserklärung Enertech AB Declaration of Box 313 Conformity S-341 26 LJUNGBY försäkrar under eget ansvar att produkten confi rme sous sa responsabilité exclusive que le produit, declare under our sole responsibility that the product, erklären in alleiniger Verantwortung, dass das Produkt, EZ250 C1 3x400V E18/ EZ250 C1 1x230V E12/ EZ250 C1 3x230V E14...