Protection Against Contamination When Installing Pipes - Daikin RXQ5P7W1B Installation Manual

Vrv iii system air conditioner
Hide thumbs Also See for RXQ5P7W1B:
Table of Contents

Advertisement

Change to configuration as in figures below
1
2
1
To indoor unit
2
Oil collects to the outmost outdoor unit when the system
stops.
Correct configuration
1
1
To indoor unit
If the piping length between the outdoor units exceeds 2 m,
create a rise of 200 mm or more in the gas line within a
length of 2 m from the kit.
If ≤2 m
-
1
≤2 m
2
1
To indoor unit
2
Piping between outdoor units
If ≥2 m
-
1
≤2 m
2
≥2 m
1
To indoor unit
2
Piping between outdoor units
5
Branching the refrigerant piping
For installation of the refrigerant branching kit, refer to the
installation manual delivered with the kit.
(See figure 13)
1
Horizontal surface
Follow the conditions listed below:
- Mount the refnet joint so that it branches either
horizontally or vertically.
- Mount the refnet header so that it branches horizontally.
RX(Y)Q5-10-12P7W1B + RXQ8P7W1B + RXYQ8P8W1B +
RXYHQ12P8W1B + RX(Y)Q14~18P7W1BA
VRVIII System air conditioner
4PW48461-1
1
2
1
Installation of the multi connection piping kit
(See figure 17)
- Install the joints horizontally, so that the caution label (1)
attached to the joint comes to the top.
Do not tilt the joint more than 15° (see view A).
Do not install the joint vertically (see view B).
- Make sure that the total length of the piping connected to
the joint is absolute straight for more than 500 mm. Only
if a straight field piping of more than 120 mm is
connected, more than 500 mm of straight section can be
ensured.
- Improper installation may lead to malfunction of the
outdoor unit.
6
Piping length restrictions
Make sure to perform the piping installation within the range of
the maximum allowable pipe length, allowable level difference
and
allowable
length
"6.6. Example of connection" on page
6.5.
Protection against contamination when
installing pipes
-
Take measures to prevent foreign materials like moisture and
contamination from mixing into the system.
Installation period
More than a month
Less than a month
Regardless of the period
-
Great caution is needed when passing copper tubes through
walls.
-
Block all gaps in the holes for passing out piping and wiring
using sealing material (field supply). (The capacity of the unit
will drop and small animals may enter the machine.)
Example: passing piping out through the front
1
2
3
After all the piping has been connected, make sure there is
no gas leak. Use nitrogen to perform a gas leak check.
after
branching
as
indicated
9.
Protection method
Pinch the pipe
Pinch or tape the pipe
1
Plug the areas marked with "
(When the piping is routed from th
front panel.)
2
Gas side piping
3
Liquid side piping
Installation manual
in
8

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents