8.14 Checks after the installation

After installation, please fill in the following form for easy daily maintenance:
No.
Model of indoor unit
1
2
3
4
5
6
Check for installation and test run
Please operate the air conditioner according to the operation manual.
Check items for test run, put mark
Gas leakage from pipe connection
Heat insulation treatment of pipe connection?
Is the connection wiring of indoor and outdoor unit firmly inserted into the terminal
block?
Is the connection wiring of indoor and outdoor firmly fixed?
Is drainage securely arranged?
Is the ground wire securely and firmly connected?
Is power supply voltage abided by electric code?
Is there any noise?
Does cooling perform normally?
Does room temperature regulator operate normally?
Factory No. of unit Site setting No.
√ in □
?
System belonged
(A/B)