Rigging - Trane Voyager YS 150–300 Installation, Operation And Maintenance Manual

Packaged rooftop – gas/ electric 121/2 – 25 tons, 60/50hz air conditioners
Table of Contents

Advertisement

Unit Weights

Rigging

WARNING
Heavy Objects!
Ensure that all the lifting equipment used is properly
rated for the weight of the unit being lifted. Each of the
cables (chains or slings), hooks, and shackles used to
lift the unit must be capable of supporting the entire
weight of the unit. Lifting cables (chains or slings) may
not be of the same length. Adjust as necessary for even
unit lift. Other lifting arrangements could cause
equipment or property damage. Failure to follow
instructions above or properly lift unit could result in
unit dropping and possibly crushing operator/
technician which could result in death or serious injury.
WARNING
Improper Unit Lift!
Test lift unit approximately 24 inches to verify proper
center of gravity lift point. To avoid dropping of unit,
reposition lifting point if unit is not level. Failure to
properly lift unit could result in unit dropping and
possibly crushing operator/technician which could
result in death or serious injury and possible equipment
or property-only damage.
Refer to
Figure 11, p. 18
and
p. 17
for typical unit operating weights rigging before
proceeding.
26. Remove the shipping crate from around the unit. Do
not remove the crating from the top of the unit.
27. Rig the unit as shown in
adequate strength lifting slings to all four lifting
brackets in the unit base rail. Do not use cables, chains,
or slings except as shown.
28. Install a lifting bar, as shown in
protect the unit and to facilitate a uniform lift. The
minimum distance between the lifting hook and the
top of the unit should be 7 feet.
29. Test-lift the unit to ensure it is properly rigged and
balanced, make any necessary rigging adjustments.
30. Lift the unit and position it into place.
31. Downflow units; align the base rail of the unit with the
curb rail while lowering the unit onto the curb. Make
sure that the gasket on the curb is not damaged while
positioning the unit.
18
Table 1, p. 17
and
Table 2,
Figure 11, p.
18. Attach
Figure 11, p.
18, to
Figure 11.
Rigging and center of gravity data
RT-SVX26K-EN

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents