Appendix A
Preliminary Site Survey
Table A-1
Sample Preliminary Site Survey (continued)
Preliminary Site Survey
Floor Mounting
How many chassis will be installed? Is
there floor space available for all of the
chassis?
Make a sketch of the area where the
chassis is to be installed and note the
chassis location.
Power
Is AC or DC power available for the
chassis? How much power is required? Is
there a connection point on the panel for
the chassis?
Is there a fuse access panel (FAP)
available for the equipment? Provide a
connection point on the FAP for each
chassis.
Will a fuse access panel be installed in
time for the routing system installation?
Provide a date when the FAP will be
installed.
Is the FAP in the same room as the
chassis?
Is there an AC power outlet (220 V or
110 V) located within 10 feet of each
chassis for PCs and test equipment?
Is there proper grounding for the
equipment? If not, when will the
grounding be available? Provide a
connection point for the grounding.
Are there any restrictions when the
equipment can be powered on or when
electrical work can be done? If so,
describe them.
Are there special requirements for power
or power cables (for example, a different
wire gauge)? If so, describe them.
Cisco Network Convergence System 6000 Series Routers Hardware Installation Guide