D. Install Back Molded Brick Panel - Herring-
bone
If a gas line is to be installed, remove the knockouts in the
inner firebox and in the outer shell on the side of your
choice. Refer to dimension drawings for location of
knockouts and Section 13.A. for gas provisions.
Refer to Figure 11.2.
Install side panel, tapered edge to the front. Align the front
edge with the front of the column (or butted to the surround
if installed).
Install two Z-brackets in the mortar lines across the top.
Tighten these and all previously installed brackets.
Install second side panel following the steps above.
Replace the smokeshield
LH Herringbone Refractory
Figure 11.2 Herringbone Molded Brick Panel
Hearth
Heatilator • Birmingham BIR42-B • 4059-681• 11/11
E. Install Side Molded Brick Panel - Herring-
bone
Remove screen rods
Remove smokeshield
Refer to Figure 11.2.
Set the grate brackets in place, 26.5 in. (673 mm) center
to center.
Install the lower back panel. Center from side to side.
Install two T-brackets stem down into mortar line to hold
lower back in position. Do not tighten.
Install upper back panel. Position bottom of panel behind
the previously installed T-brackets.
Install three T-brackets stem side up into mortar line, do
not tighten
Install two Z-brackets in the mortar lines across the top.
Tighten these and all previously installed brackets.
Back Herringbone Refractory