Press the knockout.
5.
To remove the knockout from the chassis, twist and pull it.
6.
Using a T-15 Torx screwdriver, install the dedicated iLO management port module.
7.
Install the air baffle (on page 20).
8.
Install the access panel (on page 18).
9.
Install the server into the rack
10.
Power up the server (on page 17).
11.
Expansion board option
To install the component:
Power down the server (on page 17).
1.
Remove the server from the rack (on page 17).
2.
("Installing the server into the
rack" on page 25).
Hardware options installation 36