Recommended Meter Start-Up Procedure
1.
Close the main water supply valve.
2.
Set the Cul-Flo-Valv® to the bypass position.
3.
Ensure that all faucets at the installation site are closed.
4.
Direct the drain line discharge into a bucket where flow can be observed.
Plug the transformer into a 120 Volt, 60 Hz, single-phase receptacle. The screen displays FIRST
5.
TIME SETUP.
6.
Complete the First Time Setup.
7.
Open the main supply valve.
8.
Initiate an immediate regeneration to move the control into the BACKWASH position.
9.
Refer to the section on manual cycling for information on cycling the control through its posi-
tions.
10. When in the BACKWASH position, slowly rotate the bypass to the soft water position until
water flows.
11. Allow the tank to fill slowly until water flows from the drain line.
12. When flow to drain is established, open the bypass fully. Watch the drain line discharge for
signs of resin. If signs of resin particles appear, reduce the flow. Increase the flow again when
resin no longer appears in the discharge.
13. After the BACKWASH runs clear, step the control to the REFILL position to fill the brine tank
and purge air from the brine line.
14. Complete the installation and cleanup.
15. Sanitize the unit as you leave the installation site. See "Sanitizing Procedure" on page 44.
16. Initiate an immediate regeneration, or set to regenerate at the preset time.