GE HC HP User Manual page 79

Ge network router user manual
Table of Contents

Advertisement

11. REMARKS/NOTES
12. GENERAL INFORMATION
Site accepted by:
Site approved by:
Site Acceptance Checklist Notes
The following notes provide important additional information about the Site Acceptance Checklist.
1.
Antenna Mounting
Mounting pole is of sufficient height to clear local obstructions, such as parapets, window cleaning
gantries, and lift housings.
Mounting Pole is of sufficient height, and is safely positioned, so as not to cause a safety hazard. No
person should be able to walk in front of, or look directly into the path of the microwave radio beam.
Where possible, the pole should be away from the edge of the building.
Mounting pole is secure and perpendicular. A pole that is not perpendicular may cause problems during
antenna alignment.
Mounting pole is grounded as per site specifications. All operators and site owners have specific
requirements regarding the grounding of installations. As a minimum, typical requirements are such that
any metal structure must be connected to the existing lightning protection ground of the building. Where
it extends beyond the 45-degree cone of protection of existing lightning conductors, additional lightning
protectors should be installed.
All steelwork is Galvanized or Stainless Steel, as appropriate to prevent corrosion.
MDS Intrepid-HC HP Installation and Operation
SITE ACCEPTANCE CHECKLIST
(continued)
Name:
Title:
Company:
Signature:
Date:
Name:
Title:
Company:
Signature:
Date:
3-5

Advertisement

Table of Contents
loading

Table of Contents