  • Page 1: Servicing Instructions

    57 - 115 - 144 - 201 - 259 [Tri phase] Installation, operating and servicing instructions EN • 1 664Y3500...
  • Page 2: Table Of Contents

    INDEX WARNINGS Who should read these instructions Symbols Recommendations Importants notes INTRODUCTION Description of the specifications Casing Heating body Heating elements Connection Control Electrical protection INSTRUCTIONS User data Setting up Heating system pressure Control panel legend TECHNICAL CHARACTERISTICS Electrical data Power Nominal current per phase INSTALLATION : GENERAL...
  • Page 3: Warnings

    WARNINGS WHO SHOULD READ THESE INSTRUCTIONS IMPORTANTS NOTES These instructions should be read by: - the specifying engineer - the installer The manufacturer reserves the right to change the - the user technical characteristics and specification of its - the service engineer products without notice.
  • Page 4: Introduction

    INTRODUCTION DESCRIPTION OF THE SPECIFICATIONS: CONNECTION This floor standing electric boiler is available in 5 models : The boiler is suitable for connection to most heating and water process systems, with a maximum working pressure of 4 bars and - Model 57 with a power of 57,6 kW a maximum temperature of 90°C.
  • Page 5: Instructions

    INSTRUCTIONS USER DATA • As with most boilers and heating appliances the casing and pipework can get hot during normal running so the boiler must All user controls are situated on the front panel of the boiler, not be covered and the surrounding area must be kept clear. there are no user controls inside the boiler casing.
  • Page 6: Technical Characteristics

    TECHNICAL CHARACTERISTICS Model Power 57,6 kW 115,2 kW 144 kW 201.6 kW 259,2 kW Nominal supply voltage Power circuit 3 x 400 V 3 x 400 V 3 x 400 V 3 x 400 V 3 x 400 V 1 x 230 V 1 x 230 V 1 x 230 V 1 x 230 V...
  • Page 7: Power

    TECHNICAL CHARACTERISTICS POWER Total Power Power (kW) Power (kW) Power (kW) Power (kW) Models (kW) Stage 1 Stage 2 Stage 3 Stage 4 E-Tech P / 57 14,4 14,4 14,4 14,4 57,6 E-Tech P / 115 28,8 28,8 28,8 28,8 115,2 E-Tech P / 144 36,0...
  • Page 8: Installation : General

    INSTALLATION : GENERAL DIMENSIONS Models Heating connection E-Tech P / 57 1495 2” [F] E-Tech P / 115 1495 2” [F] E-Tech P / 144 1495 2” [F] E-Tech P / 201 1495 1100 DN 100 E-Tech P / 259 1495 1100 DN 100...
  • Page 9: Installation : Hydraulic

    INSTALLATION : HYDRAULIC HEATING CONNECTION Adjustable temperature 1 = 25°C 2 = 40°C 3 = 55°C 4 = 70°C 5 = 85°C 0 - 90°C = 5A HEATING CONNECTION + DHW (2 Circulating pumps) 1 = 25°C The controller is factory programmed with DHW 2 = 40°C priority.
  • Page 10: Installation : Electric Supply

    INSTALLATION : ELECTRIC SUPPLY WARNING !!! 8. Remount the bottom protection and close the power Size the flow rate in the hydraulic circuit to ensure a 10°C connections box. maximum ΔT. GENERAL SAFETY RULES • The boiler must be installed by a competent person or registered company.
  • Page 11: Sizing Of Supply Wires

    INSTALLATION : ELECTRIC SUPPLY SIZING OF SUPPLY WIRES POWER VARIATION (kW) RELATIVE TO VOLTAGE The supply wires are sized depending of the type and current of the MCB. The MCB last is sized depending of the nominal current of the boiler. The admissible current of the supply wires depends Models 3 x 380 V 3 x 400 V...
  • Page 12: Wiring Diagrams

    INSTALLATION : ELECTRIC SUPPLY WIRING DIAGRAMS 27 29 3 Amp 28 30 Y/Gr Y/Gr Y/Gr Q5 Q6 Q7 Q8 : Blue ON/OFF switch High temperature : Black Manual reset high limit thermostat Water pressure : Brown Water pressure switch Common alarm signal : Grey Summer / Winter switch Boiler demand...
  • Page 13: Power Limitation

    INSTALLATION : ELECTRIC SUPPLY POWER LIMITATION : Any change to the power limitation will alter the The maximum power of the boiler can be limited from 25 to 100% current once the boiler has switched to stand-by (busy by acting on the SW1, SW2 electrical bridges as mentioned in signal is OFF).
  • Page 14 INSTALLATION : ELECTRIC SUPPLY E-TECH P / 57 POWER WIRING / MODEL : 35 mm F-100A 20 x 5 mm BF09 SMB 52 K4 - 1 K4 - 1 Q4 - 1 Stage 4 Stage 4 25 23 K4 - 1 K3 - 1 K3 - 1 BF09...
  • Page 15 INSTALLATION : ELECTRIC SUPPLY E-TECH P / 115 POWER WIRING / MODEL : 95 mm F-200A K4 - 2 K4 - 2 Stage 4 Stage 4 K4 - 1 K4 - 1 Stage 4 Stage 4 20 x 5 mm BF09 SMB 52 K3 - 2...
  • Page 16 INSTALLATION : ELECTRIC SUPPLY E-TECH P / 144 POWER WIRING / MODEL : 120 mm F-250A 20 x 5 mm Q4 - 2 Q4 - 1 K4 - 2 K4 - 1 Q3 - 2 Q3 - 1 K3 - 2 K3 - 1 Q2 - 3 Q2 - 2...
  • Page 17 INSTALLATION : ELECTRIC SUPPLY E-TECH P / 144 POWER WIRING / MODEL : K4 - 2 K4 - 2 Stage 4 Stage 4 K4 - 1 K4 - 1 Stage 4 Stage 4 BF09 SMB 52 K3 - 2 K3 - 2 Stage 3 Stage 3 25 23...
  • Page 18 INSTALLATION : ELECTRIC SUPPLY E-TECH P / 201 POWER WIRING / MODEL : 185 mm F-315A 30 x 5 mm Q4 - 3 Q4 - 2 Q4 - 1 K4 - 3 K4 - 2 K4 - 1 Q3 - 3 Q3 - 2 Q3 - 1 K3 - 3...
  • Page 19 INSTALLATION : ELECTRIC SUPPLY E-TECH P / 201 POWER WIRING / MODEL : BF09 SMB 52 25 23 K4 - 3 K4 - 3 K4 - 3 Stage 4 Stage 4 BF09 SMB 52 K4 - 2 K4 - 2 25 23 K4 - 2 Stage 4...
  • Page 20 INSTALLATION : ELECTRIC SUPPLY E-TECH P / 259 POWER WIRING / MODEL : 240 mm F-400A 30 x 5 mm Q4 - 5 Q4 - 4 Q4 - 3 Q4 - 2 Q4 - 1 K4 - 5 K4 - 4 K4 - 3 K4 - 2 K4 - 1...
  • Page 21 INSTALLATION : ELECTRIC SUPPLY E-TECH P / 259 POWER WIRING / MODEL : K4 - 5 K4 - 5 Stage 4 Stage 4 K4 - 4 K4 - 4 Stage 4 Stage 4 K4 - 3 K4 - 3 Stage 4 Stage 4 K4 - 2 K4 - 2...
  • Page 22: Commissioning

    3. Switch on local isolator to boiler boiler. If installing the boiler onto an existing system, ACV 4. Turn the boiler on using the ON/OFF switch recommend that an approved system cleaner is used.
  • Page 23: Maintenance

    For safety reasons it is recommended that the boiler is serviced annually and that servicing is carried out by a qualified service engineer. Models Fuses ACV code Before carrying out any work on the system ensure that the boiler is cool and all E-Tech P / 57 100 A 5476C006 electrical supplies are isolated.