PVI Industries PV 17-A Startup Manual

Gas-fired water heaters

Advertisement

**FOR DETAILED INFORMATION SEE INSTALLATION & MAINTENANCE MANUAL **
1.
Visually inspect water heater and components for damage and proper installation.
2.
Check all electrical connections for tightness and proper voltage.
3.
Check water heater tank to make sure it is full of water. (Remove air through T&P valve).
4.
Pull nozzle assembly from burner and check gap settings on electrodes (see I&M).
5.
While nozzle is removed, look inside through burner for obstructions.
6.
Check fan rotation.
7.
Check air shutter setting (guideline on burner tag).
8.
Drill hole in vent pipe 12" to 24" from heater flue outlet but below draft regulator
(for analysis equipment).
9.
Attach voltmeter to controller to record flame signal.
10.
Check inlet static gas pressure before gas train (see rating on heater decal).
11.
Attach manometer to manifold to read pressure (tapping closest to burner).
12.
Turn off main manual gas valve and start burner on pilot (if burner has separate pilot).
a) Set pilot to give good flame signal with just enough gas to reliably light pilot.
NOTE: If there is no pilot, set gas pressure (guideline on burner tag).
b) Slowly open main gas and set gas pressure (guideline on burner tag).
c) Check flame signal (should be in range called for by control).
13.
Check inlet flow gas pressure before gas train.
NOTE: Should meet or exceed minimum rating listed on heater decal.
14.
Check vent draft in stack (should be negative .02" to negative .06" W.C.).
15.
Perform flue gas analysis after achieving water temperatures above 120
NOTE: Modulating burners should be checked at 25% increments.
a) Net stack temperature should be 3 00
b) O2 should be from 4% to 7% (atmospheric units tested below draft diverter).
c) CO2 should be from 8% to 10% (atmospheric units tested below draft diverter).
d) CO should not exceed 200 PPM (atmospheric units tested below draft diverter).
NOTE: A complete and proper start-up includes checking the operation of all controls and limits (i.e. airflow
switch, LWCO, thermostats, and modulating controls), and filling out the entire start-up report. All discrepancies
should be reported to the PVI Customer Service Department (800-433-5654) from the job site and detailed on
the comment section of the start-up report. Attach notes to report if needed. Also, please call if you have any
questions or need assistance.
PVI Industries, Incorporated

START-UP OF GAS-FIRED WATER HEATERS

º
F - 400
Start-Up of Gas-Fired Water Heaters
º
F (read in stack, all units).
PV 17-A
º
F.
May 1998

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the PV 17-A and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for PVI Industries PV 17-A

  • Page 1 PVI Customer Service Department (800-433-5654) from the job site and detailed on the comment section of the start-up report. Attach notes to report if needed. Also, please call if you have any questions or need assistance. PVI Industries, Incorporated Start-Up of Gas-Fired Water Heaters May 1998...
  • Page 2 START-UP REPORT GAS FIRED NON-CONDENSING WATER HEATERS ® ® Atmospheric - MAXIM - TURBOPOWER Warning: Startup must be performed by a qualified service installer, service agency or the gas supplier. Model Number: Serial Number: Job Name: Address: GENERAL INFORMATION Restart? Installation is: Replacement/Renovation Indoor...
  • Page 3 Model Number: Serial Number: GAS SUPPLY Type of gas: Natural Gas Supply Pipe Size: inches Inlet Static Gas Pressure: “W.C. (14” W.C. maximum) Inlet Flow Gas Pressure: “W.C. (see data label) Combination Gas Pressure Switch Setting: High / Low “W.C. COMBUSTION ANALYSIS BURNER MODEL NO.: BURNER SERIAL NO.:...

Table of Contents