Electrical
when completed
Are two AC outlets (on different lines) available for the proposed
equipment?
Does the input voltage correspond to equipment specifications?
Are the input circuit breakers adequate for equipment loads?
Does the input frequency correspond to equipment specifications?
Are lightning arresters installed?
Have all sources of electrical interferences been corrected?
Air-Conditioning
when completed
Can the temperature be maintained between 16 and 32 C?
Can temperature changes be held to less that 10 C per hour?
Can humidity level be maintained between 20% and 80% percent?
Building Access and Security
when completed
Is there access control to the computer room?
Is there access control for the customer site?
Are any stair-walkers, lifts, ramps, floor coverings, or ladders
required to install the equipment?
Define: _________________________________________
Will the equipment fit through all doors, corridors, and in lifts,
both in size and weight?
Does the building have a loading dock?
Maximum access height is _____m.
Site prep team and tasks
Yes
No
Reference
page 36
page 36
page 36
page 36
page 51
page 51
Yes
No
Reference
page 69
page 71
page 71
Yes
No
Reference
page 27
page 27
page 27
page 27
page 27
15