Pre-Commissioning
Before Going to the Site
Gather site information, design records, installation guides, and required forms before visiting the customer.
ICAM Commissioning Form Prerequisites
Complete client and site details in commissioning forms, including customer name, installer, and installation type.
Once on Site
Tasks to be performed after arriving at the customer's site, including checks and initial setup.
System Configuration and Setting Thresholds
IFT Detector Configuration
Configure IFT detectors using Xtralis VSC software or a display panel, covering main menu modes and access codes.
ILS Detector Configuration
Configure ILS detectors via user interface or VSC software, covering programmable functions like sensitivity and thresholds.
IAS Detector Configuration
Configure IAS detectors via user interface or VSC software, focusing on air flow parameters and programmable functions.
System Integrity Test
Performance-based Smoke Testing
Methods to prove pipe network integrity and measure response time, including various smoke test types.
Testing Devices
Tools and methods for testing IFT detector outputs using diagnostic tests.
Documenting Test Results
Recording and forwarding test outcomes on commissioning forms.