Huawei LUNA2000-213KTL-H0 User Manual
Huawei LUNA2000-213KTL-H0 User Manual

Huawei LUNA2000-213KTL-H0 User Manual

Smart power control system
Hide thumbs Also See for LUNA2000-213KTL-H0:
Table of Contents

Advertisement

Quick Links

LUNA2000-213KTL-H0 Smart Power Control
System
User Manual
Issue
04
Date
2024-12-30
HUAWEI TECHNOLOGIES CO., LTD.

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the LUNA2000-213KTL-H0 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Huawei LUNA2000-213KTL-H0

  • Page 1 LUNA2000-213KTL-H0 Smart Power Control System User Manual Issue Date 2024-12-30 HUAWEI TECHNOLOGIES CO., LTD.
  • Page 2 Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
  • Page 3: About This Document

    Purpose This document describes the installation, electrical connections, commissioning, maintenance, and troubleshooting of LUNA2000-213KTL-H0 Smart Power Control System (also referred to as Smart PCS). Before installing and operating the Smart PCS, ensure that you are familiar with the features, functions, and safety precautions provided in this document.
  • Page 4: Change History

    LUNA2000-213KTL-H0 Smart Power Control System User Manual About This Document Symbol Description Supplements the important information in the main text. NOTE is used to address information not related to personal injury, equipment damage, and environment deterioration. Change History Changes between document issues are cumulative. The latest document issue contains all the changes made in earlier issues.
  • Page 5 LUNA2000-213KTL-H0 Smart Power Control System User Manual About This Document Updated 4.2.3 Foundation Requirements. Updated 4.2.4 Clearance Requirements. Updated 4.3 Preparing Tools. Updated 4.6 Mounting the Smart PCS on a Base Support. Updated 5.6.2 Installing COM Communications Cables. Updated 8.5 Replacing the Smart PCS.
  • Page 6: Table Of Contents

    LUNA2000-213KTL-H0 Smart Power Control System User Manual Contents Contents About This Document........................ ii 1 Safety Information........................1 1.1 Personal Safety..................................2 1.2 Electrical Safety..................................4 1.3 Environment Requirements..............................6 1.4 Mechanical Safety................................... 8 2 Product Description......................13 2.1 Model......................................13 2.2 Networking Application..............................15 2.3 Appearance.....................................
  • Page 7 LUNA2000-213KTL-H0 Smart Power Control System User Manual Contents 5.4 Installing DC Power Cables............................... 50 5.5 Installing AC Power Cables..............................53 5.6 Installing Communications Cables..........................57 5.6.1 Installing FE Communications Cables........................58 5.6.2 Installing COM Communications Cables........................63 6 Check Before Power-On....................... 71 7 Power-On and Commissioning...................
  • Page 8: Safety Information

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 1 Safety Information Safety Information Statement Before transporting, storing, installing, operating, using, and/or maintaining the equipment, read this document, strictly follow the instructions provided herein, and follow all the safety instructions on the equipment and in this document.
  • Page 9: Personal Safety

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 1 Safety Information ● The equipment is installed or used in environments that do not comply with international, national, or regional standards. ● The equipment is installed or used by unqualified personnel. ●...
  • Page 10: General Requirements

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 1 Safety Information WARNING During operations, wear personal protective equipment such as protective clothing, insulated shoes, goggles, safety helmets, and insulated gloves. Figure 1-1 Personal protective equipment General Requirements ● Do not stop protective devices. Pay attention to the warnings, cautions, and related precautionary measures in this document and on the equipment.
  • Page 11: Electrical Safety

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 1 Safety Information – Trained personnel: personnel who are trained in technology and safety, have required experience, are aware of possible hazards on themselves in certain operations, and are able to take protective measures to minimize the hazards on themselves and other people ●...
  • Page 12 LUNA2000-213KTL-H0 Smart Power Control System User Manual 1 Safety Information CA UTION Do not route cables near the air intake or exhaust vents of the equipment. General Requirements ● Follow the procedures described in the document for installation, operation, and maintenance. Do not reconstruct or alter the equipment, add components, or change the installation sequence without permission.
  • Page 13: Cabling Requirements

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 1 Safety Information ● Do not scrawl, damage, or block any labels or nameplates on the equipment. Promptly replace labels that have worn out. ● Do not use solvents such as water, alcohol, or oil to clean electrical components inside or outside of the equipment.
  • Page 14 LUNA2000-213KTL-H0 Smart Power Control System User Manual 1 Safety Information D ANGER Do not store any flammable or explosive materials in the equipment area. D ANGER Do not place the equipment near heat sources or fire sources, such as smoke, candles, heaters, or other heating devices.
  • Page 15: Mechanical Safety

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 1 Safety Information ● Do not install the equipment in an area with strong vibration, noise, or electromagnetic interference. The equipment shall be installed in an environment with a magnetic field strength less than 4 Gauss. If the magnetic field strength is greater than or equal to 4 Gauss, the equipment may fail to work properly.
  • Page 16 LUNA2000-213KTL-H0 Smart Power Control System User Manual 1 Safety Information ● Do not install other devices on the top of the equipment without evaluation by the Company. ● When performing operations over the top of the equipment, take measures to protect the equipment against damage.
  • Page 17: Using Ladders

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 1 Safety Information Using Ladders ● Use wooden or insulated ladders when you need to perform live-line working at heights. ● Platform ladders with protective rails are preferred. Single ladders are not recommended.
  • Page 18: Drilling Holes

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 1 Safety Information Hoisting ● Only trained and qualified personnel are allowed to perform hoisting operations. ● Install temporary warning signs or fences to isolate the hoisting area. ● Ensure that the foundation where hoisting is performed on meets the load- bearing requirements.
  • Page 19 LUNA2000-213KTL-H0 Smart Power Control System User Manual 1 Safety Information ● To avoid short circuits or other risks, do not drill holes into buried pipes or cables. ● When drilling holes, protect the equipment from shavings. After drilling, clean up any shavings.
  • Page 20: Product Description

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 2 Product Description Product Description On-Grid ● The Smart PCS implements rectification and inversion through a three-phase three-level converter. ● The rectified output is converted from three-phase AC power to DC power and then stored in the energy storage system (ESS).
  • Page 21 LUNA2000-213KTL-H0 Smart Power Control System User Manual 2 Product Description Meaning Description Topology TL: transformerless identifier Product series H0: product series with the 1500 V DC voltage identifier Model Label Positions You can obtain the device model from the model label on the outer packaging and the nameplate on the side of the enclosure.
  • Page 22: Networking Application

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 2 Product Description Figure 2-3 Position of the nameplate (1) Position of the nameplate 2.2 Networking Application The system consists of the ESS, Smart Power Control System (PCS), Smart Transformer Station (STS), Distribution Transformer (DTS), and other equipment.
  • Page 23 LUNA2000-213KTL-H0 Smart Power Control System User Manual 2 Product Description On-Grid Scenario Figure 2-4 ESS-only solution (separate SACU) networking architecture Figure 2-5 Networking architecture of the PV+ESS medium-voltage coupling solution (separate SACU) NO TE The Smart PCS shall be connected to a dedicated power transformer and must not be connected to low-voltage overhead lines.
  • Page 24 LUNA2000-213KTL-H0 Smart Power Control System User Manual 2 Product Description NO TE The grid-forming function of the Smart PCS is disabled by default. If the grid-forming function is required, purchase the license and load the license by referring to License SmartLogger3000 User Manual .
  • Page 25: Earthing System

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 2 Product Description Parameter Description Rated Same as above operating capacity of equipment (kW) Earthing System The Smart PCS supports the IT earthing system. Figure 2-6 Earthing system Issue 04 (2024-12-30) Copyright © Huawei Technologies Co., Ltd.
  • Page 26: Appearance

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 2 Product Description 2.3 Appearance Appearance and Ports Figure 2-7 Appearance and ports (1) AC maintenance (2) Communications (3) Panel compartment cable hole (FE) (4) Communications cable (5) DC maintenance (6) LED indicators...
  • Page 27: Indicator Description

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 2 Product Description Note [1]: The security Torx wrench is delivered with the device and is tied to the bracket on the top of the device. Remove the security Torx wrench from the bracket and keep it safe.
  • Page 28 LUNA2000-213KTL-H0 Smart Power Control System User Manual 2 Product Description Table 2-2 LED indicator description Category Status (Blinking Fast: On Meaning for 0.2s and Off for 0.2s; Blinking Slowly: On for 1s and Off for 1s) DC indication Steady green...
  • Page 29: Circuit Diagram

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 2 Product Description NO TE ● If the DC indicator and running indicator do not blink red fast and the fault/ maintenance indicator is steady red, replace parts or the entire device. ● Local maintenance refers to the operation that requires inserting a WLAN module into the USB port of the device, for example, connecting to the FusionSolar app through the WLAN module.
  • Page 30: Label Description

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 2 Product Description Table 2-3 Working mode description Working Description Mode Standby The Smart PCS enters standby mode when the external environment does not meet the operating requirements. In standby mode: ● The Smart PCS continuously detects its operation status. Once the operation conditions are met, the Smart PCS enters operating mode.
  • Page 31 LUNA2000-213KTL-H0 Smart Power Control System User Manual 2 Product Description Symbol Name Meaning Delayed discharge ● High voltage may occur after the device is powered on. Only qualified and trained electrical technicians are allowed to install and operate the device.
  • Page 32: Storage Requirements

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 3 Storage Requirements Storage Requirements NO TICE ● Store Smart PCSs according to the storage requirements. Device damage caused by unqualified storage conditions is not covered under the warranty. ● Do not store Smart PCSs without outer packaging.
  • Page 33: Installation

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 4 Installation Installation 4.1 Installation Modes The Smart PCS can be mounted on a base support or rear bracket. Table 4-1 Installation modes Installation Mode Quantity Source Base Base support Purchased from the...
  • Page 34 LUNA2000-213KTL-H0 Smart Power Control System User Manual 4 Installation ● Do not install the Smart PCS in noise-sensitive areas (such as residential areas, office areas, and schools) to avoid complaints. If the preceding areas are unavoidable, the distance between the installation position and noise- sensitive areas must be greater than or equal to 40 m.
  • Page 35: Mounting Structure Requirements

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 4 Installation Smart PCS provides self-protection in high-temperature environments. The power of the Smart PCS may decrease as the ambient temperature increases. ● Do not install the equipment in an area with strong vibration, noise, or electromagnetic interference.
  • Page 36: Foundation Requirements

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 4 Installation Figure 4-1 Mounting structure 4.2.3 Foundation Requirements A foundation is required only in the base support-mounting scenario. Before installation, build concrete platforms and trenches on the selected ground. The foundation construction requirements are as follows: ●...
  • Page 37 LUNA2000-213KTL-H0 Smart Power Control System User Manual 4 Installation Table 4-2 Checklist Check Item Acceptance Criteria Cabling space ● If no maintenance space at the bottom is required, it at the bottom is recommended that the cabling space at the bottom of the base support be greater than or equal to 1.1 m.
  • Page 38: Clearance Requirements

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 4 Installation 4.2.4 Clearance Requirements Reserve sufficient clearance around the Smart PCS for installation and heat dissipation. ● Base support-mounted Figure 4-3 Clearances NO TE For ease of installation, cable connection, and maintenance, you are advised to reserve at least 1500 mm clearance.
  • Page 39: Angle Requirements

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 4 Installation Figure 4-5 Horizontal installation mode (recommended) 4.2.5 Angle Requirements Figure 4-6 Installation angle 4.3 Preparing Tools Before installation, the following tools need to be prepared. Issue 04 (2024-12-30) Copyright © Huawei Technologies Co., Ltd.
  • Page 40: Installation Tools

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 4 Installation Installation Tools Hammer drill Drill bit (Ф14 mm Insulated torque Phillips insulated and Ф16 mm) socket wrench torque screwdriver (including an extension bar ≥ 50 Wire stripper Rubber mallet Utility knife...
  • Page 41: Personal Protective Equipment (Ppe)

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 4 Installation Heat shrink tubing Heat gun Ladder Digital multimeter DC voltage measurement range ≥ 1500 V DC AC voltage measurement range ≥ 800 V AC Crane Lifting sling Length ≥ 1.8 m Hoisting capability ≥...
  • Page 42: Pre-Installation Checks

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 4 Installation 4.4 Pre-installation Checks NO TICE ● After placing the equipment in the installation position, unpack it with care to prevent scratches. Keep the equipment stable during unpacking. Checking the Outer Packing Before unpacking the device, check the outer packing for damage, such as holes and cracks, and check the device model.
  • Page 43 LUNA2000-213KTL-H0 Smart Power Control System User Manual 4 Installation NO TICE ● Four persons or appropriate transportation tools are required to move the device. ● Place a foam pad or cardboard under the device to protect its enclosure from damage.
  • Page 44 LUNA2000-213KTL-H0 Smart Power Control System User Manual 4 Installation (1) Lifting handle screw hole (2) Mounting bracket screw holes Procedure Step 1 Take the device out of the packing case and move it to the specified position. Figure 4-7 Using the lifting handles...
  • Page 45: Mounting The Smart Pcs On A Base Support

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 4 Installation Figure 4-9 Hoisting ----End 4.6 Mounting the Smart PCS on a Base Support Precautions ● To prevent dust inhalation or contact with eyes, wear safety goggles and a dust mask when drilling holes.
  • Page 46 LUNA2000-213KTL-H0 Smart Power Control System User Manual 4 Installation Base Support ● The base support needs to be purchased separately from the Company. ● The dimensions (L x W x H) of the base support is 2380 mm x 916 mm x 450 ●...
  • Page 47 LUNA2000-213KTL-H0 Smart Power Control System User Manual 4 Installation Figure 4-12 Manual handling Figure 4-13 Hoisting Step 3 Check whether there is a gap between the base support and the concrete platforms. If yes, level the base support using leveling spacers delivered with the product.
  • Page 48 LUNA2000-213KTL-H0 Smart Power Control System User Manual 4 Installation Figure 4-14 Securing the base support After the base support is secured, verify the installation to ensure normal use of the base support and smooth subsequent installation. Table 4-4 Verifying the installation...
  • Page 49: Mounting The Smart Pcs On A Rear Bracket

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 4 Installation Step 6 Install the other Smart PCSs in the same way. For details, see the figure in Step Step 7 Install the connecting brackets delivered with the base support. The connecting brackets need to be installed on both the DC and AC sides.
  • Page 50 LUNA2000-213KTL-H0 Smart Power Control System User Manual 4 Installation Figure 4-17 Hole dimensions Procedure Step 1 Install the mounting bracket. Figure 4-18 Installing the mounting bracket NO TE If the bolt length does not meet the installation requirements, prepare M12 bolts and use them together with the delivered M12 nuts.
  • Page 51 LUNA2000-213KTL-H0 Smart Power Control System User Manual 4 Installation Figure 4-19 Installing the mounting ears Step 3 (Optional) If the device needs to be moved manually, adjust the positions of the lifting handles at the bottom of the device. Figure 4-20 Adjusting the positions of lifting handles Step 4 Install the device on the mounting bracket.
  • Page 52 LUNA2000-213KTL-H0 Smart Power Control System User Manual 4 Installation Figure 4-21 Installing the device on the mounting bracket Step 5 Tighten the two screws at the bottom of the device. Figure 4-22 Installing the Smart PCS ----End Issue 04 (2024-12-30)
  • Page 53: Cable Installation

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation Cable Installation 5.1 Precautions D ANGER ● Before connecting cables, ensure that the external switches on the AC and DC sides of the Smart PCS are off to disconnect all external connections of the Smart PCS.
  • Page 54: Preparing Cables

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation NO TE The cable colors shown in the electrical connection diagrams provided in this section are for reference only. Select cables in accordance with local cable specifications (green-and-yellow cables are only used for protective earthing). The factors that affect cable selection include the rated current, cable type, routing mode, ambient temperature, and maximum expected line loss.
  • Page 55: Installing A Pe Cable

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation Cable Type Conductor Outer Descripti Cross-Sectional Diameter Area AC power Single-core outdoor cable and M12 15–35 mm 70–240 mm cable OT/DT terminal (single- core) Communi FE/COM communications cable: CAT 4.5–7.5 mm...
  • Page 56 LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation NO TE ● Install the grounding brackets between the Smart PCSs and the base support on either the DC side or the AC side. ● There is one ground point on each side of the base support. It is recommended that both ground points be grounded.
  • Page 57: Installing Dc Power Cables

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation ● Rear bracket-mounted: Install the PE cable on either the AC side or the DC side. Figure 5-3 Installing a PE cable Follow-up Procedure To enhance the corrosion resistance of a ground terminal, apply silicone grease or paint on it after connecting the PE cable.
  • Page 58 LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation Procedure Step 1 Prepare the cables. For details, see A Crimping an OT or DT Terminal. Step 2 Open the DC maintenance compartment door. Remove the accessories from the DC maintenance compartment and store them properly for future use.
  • Page 59 LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation Figure 5-5 Removing a rubber ring Step 4 Connect the DC power cables to the terminal block and ensure that the cables are securely connected. Figure 5-6 Single-core cable connection Issue 04 (2024-12-30) Copyright ©...
  • Page 60: Installing Ac Power Cables

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation Figure 5-7 Multi-core cable connection ----End 5.5 Installing AC Power Cables Precautions A three-phase AC switch shall be installed on the AC side of the Smart PCS. To ensure that the Smart PCS can be safely disconnected from the power grid when an exception occurs, select a proper overcurrent protection device in compliance with local power distribution regulations.
  • Page 61 LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation CA UTION Each Smart PCS must be equipped with an AC output switch. If this requirement cannot be met, a maximum of two Smart PCSs can be connected to one AC output switch.
  • Page 62 LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation Figure 5-8 Opening the AC maintenance compartment door Step 3 Remove a rubber ring based on the cable diameter range. Cut off the joints between rubber rings using scissors and then remove the rubber ring. All rubber rings are removed in the same way.
  • Page 63 LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation Figure 5-10 Single-core cable connection Figure 5-11 Multi-core cable connection NO TE It is recommended that the stripped length of the L2 wire be 15 mm shorter than that of the L1 or L3 wire.
  • Page 64: Installing Communications Cables

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation ----End 5.6 Installing Communications Cables To ensure normal communication, install cables to both FE and COM communications ports. NO TICE ● For FE communications ports, all Smart PCSs need to be connected in a ring network in hand-in-hand mode using FE communications cables.
  • Page 65: Communications Ports

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation Communications Ports Figure 5-12 Port description (1) FE network port 2 (2) FE network port 1 (3) COM network port 1 (4) COM network port 2 5.6.1 Installing FE Communications Cables The Smart PCSs connect to the SACU (model: SmartACU2000D-D-11) over FE communications cables.
  • Page 66 LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation NO TE If the length of the delivered cable does not meet the requirement, prepare a network cable by yourself or use the delivered connector and a cable prepared by yourself to crimp a network cable.
  • Page 67 LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation Figure 5-16 Connecting a plastic housing (1) Shielded plug (2) Plastic housing (3) Coupling nut (4) Sealing ring (5) Sealing nut Step 3 Insert the sealing ring into the plastic housing and secure the coupling nut to the plastic housing.
  • Page 68 LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation Figure 5-19 Connecting FE Communications Cables Step 6 Bind the FE communications cables in the AC maintenance compartment. Figure 5-20 Binding the FE communications cables Step 7 Retract the support bar, close the maintenance compartment door, and tighten the two screws on the door.
  • Page 69 LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation NO TICE ● Before closing a maintenance compartment door, check that the cables are connected correctly and securely, close the terminal block cover, and remove any foreign object from the maintenance compartment.
  • Page 70: Installing Com Communications Cables

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation Figure 5-22 Binding FE communications cables ----End 5.6.2 Installing COM Communications Cables Context ● The COM communications port transmits CAN signals and dry contact protection signals. ● CAN and dry contacts establish a channel for communication between the Smart PCS and the ESS battery rack and for fast protection.
  • Page 71 LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation Figure 5-24 Connection for two Smart PCSs per battery rack Figure 5-25 Connection for four Smart PCSs per battery rack Communications Port Pin Definitions Figure 5-26 Communications port Table 5-2 CAN and dry contact pin definitions...
  • Page 72 LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation NO TE Dry contact protection logic: The external contact is closed by default. If the external contact is open, an alarm is generated and the Smart PCS shuts down automatically.
  • Page 73 LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation (5) White-and-blue (6) Green (7) White-and- (8) Brown brown Step 2 Insert the plug through the sealing nut, sealing ring, coupling nut, and plastic housing in sequence. Figure 5-29 Connecting a plastic housing...
  • Page 74 LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation Figure 5-32 Connecting COM communications cables Step 6 Bind the COM communications cables in the DC maintenance compartment. Figure 5-33 Binding the COM communications cables Step 7 Retract the support bar, close the maintenance compartment door, and tighten the two screws on the door.
  • Page 75 LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation NO TICE ● Before closing a maintenance compartment door, check that the cables are connected correctly and securely, close the terminal block cover, and remove any foreign object from the maintenance compartment.
  • Page 76 LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation Figure 5-35 Cable binding for one Smart PCS per battery rack Figure 5-36 Cable binding for two Smart PCSs per battery rack Issue 04 (2024-12-30) Copyright © Huawei Technologies Co., Ltd.
  • Page 77 LUNA2000-213KTL-H0 Smart Power Control System User Manual 5 Cable Installation Figure 5-37 Cable binding for four Smart PCSs per battery rack ----End Issue 04 (2024-12-30) Copyright © Huawei Technologies Co., Ltd.
  • Page 78: Check Before Power-On

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 6 Check Before Power-On Check Before Power-On Check the items listed in the following table. In case of any nonconforming items, rectify the fault and reinstall the parts. Then, check the items listed in the following table again until all the items pass the check.
  • Page 79 LUNA2000-213KTL-H0 Smart Power Control System User Manual 6 Check Before Power-On Check Acceptance Criteria Item The waterproof plugs on the unused USB, COM, and FE ports are secured. Issue 04 (2024-12-30) Copyright © Huawei Technologies Co., Ltd.
  • Page 80: Power-On And Commissioning

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 7 Power-On and Commissioning Power-On and Commissioning 7.1 Powering On the Smart PCS Prerequisites ● Ensure that all the items in 6 Check Before Power-On are checked and meet the requirements before power-on.
  • Page 81 LUNA2000-213KTL-H0 Smart Power Control System User Manual 7 Power-On and Commissioning NO TICE The recommended specifications for the AC switch between the AC side of the Smart PCS and the transformer station are as follows. Select a power distribution switch that complies with local regulations based on actual application scenarios.
  • Page 82: Commissioning The Smart Pcs

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 7 Power-On and Commissioning Category Status (Blinking Fast: On Meaning for 0.2s and Off for 0.2s; Blinking Slowly: On for 1s and Off for 1s) The DC side is not properly connected, or the auxiliary power supply inside the device is not working.
  • Page 83: Setting The Hot Standby Mode

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 7 Power-On and Commissioning ● FusionSolar app: The app is used for local commissioning, mainly to modify the parameters and upgrade the software version of a single Smart PCS. For details, see the FusionSolar App and SUN2000 App Device Commissioning Guide.
  • Page 84 LUNA2000-213KTL-H0 Smart Power Control System User Manual 7 Power-On and Commissioning Table 7-2 Hot standby mode parameter settings Parameter Description Entry/Exit Application Condition Scenario Zero-power No hot standby. The Scenarios where fast operation Smart PCS is response to power operating with zero scheduling is power.
  • Page 85: Device Maintenance

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 8 Device Maintenance Device Maintenance 8.1 Routine Maintenance Precautions D ANGER ● Wear personal protective equipment and use dedicated insulated tools to avoid electric shocks or short circuits. WARNING ● Before performing maintenance, power off the equipment, follow the instructions on the delayed discharge label, and wait for a period of time as specified to ensure that the equipment is not energized.
  • Page 86 LUNA2000-213KTL-H0 Smart Power Control System User Manual 8 Device Maintenance Table 8-1 Maintenance checklist Check Item Check Method Maintenance Interval Alarm Check alarms on the app, SmartLogger, or Routine maintenance management system. ● Cleanness of the ● Check whether there is dust on the air...
  • Page 87: Powering Off The System

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 8 Device Maintenance Removing the Baffle Plate from the Air Intake Vent Figure 8-1 Removing the baffle plate NO TICE After the cleaning is complete, reinstall the baffle plate to the air intake vent.
  • Page 88: Follow-Up Procedure

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 8 Device Maintenance Step 5 Turn off the DC switch between the Smart PCS and the ESS. Step 6 Open the DC maintenance compartment door, install a support bar, and use a multimeter to check the voltage between DC terminal blocks. Ensure that the DC side of the Smart PCS is powered off.
  • Page 89: Replacing A Fan

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 8 Device Maintenance 8.4 Replacing a Fan Precautions ● Before replacing a fan, power off the Smart PCS. ● When replacing a fan, use insulated tools and wear PPE. Procedure Step 1 Remove the screws from the fan tray and store them properly. Pull out the fan tray until it is flush with the maintenance compartments of the Smart PCS.
  • Page 90 LUNA2000-213KTL-H0 Smart Power Control System User Manual 8 Device Maintenance Figure 8-4 Disconnecting cables Step 3 Pull out the fan tray completely. Figure 8-5 Pulling out the fan tray (2) Step 4 Remove cable ties of the faulty fan. ●...
  • Page 91 LUNA2000-213KTL-H0 Smart Power Control System User Manual 8 Device Maintenance Figure 8-6 Removing cable ties from FAN 1 ● FAN 2 is faulty. Figure 8-7 Removing cable ties from FAN 2 ● FAN 3 is faulty. Figure 8-8 Removing cable ties from FAN 3 Step 5 Remove the faulty fan (FAN 1 is used as an example).
  • Page 92 LUNA2000-213KTL-H0 Smart Power Control System User Manual 8 Device Maintenance Step 6 Install a new fan (FAN 1 is used as an example). Figure 8-10 Installing a fan Step 7 Bind the fan cables. ● Binding positions for FAN 1 Figure 8-11 Binding the cables of FAN 1 ●...
  • Page 93 LUNA2000-213KTL-H0 Smart Power Control System User Manual 8 Device Maintenance Figure 8-13 Binding the cables of FAN 3 Step 8 Push in the fan tray until the fan baffle plate is flush with the Smart PCS enclosure. NO TE If the fan gets stuck when being pushed in, slightly lift the fan tray.
  • Page 94 LUNA2000-213KTL-H0 Smart Power Control System User Manual 8 Device Maintenance Figure 8-15 Binding cables Step 10 Push in the fan tray completely and tighten the screws. Figure 8-16 Reinstalling the fan tray ----End Issue 04 (2024-12-30) Copyright © Huawei Technologies Co., Ltd.
  • Page 95: Replacing The Smart Pcs

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 8 Device Maintenance 8.5 Replacing the Smart PCS Context Replace the device if its enclosure is severely damaged or the hardware is faulty due to external forces. Procedure Step 1 Send a shutdown command on the FusionSolar app, SmartLogger, or management system.
  • Page 96 LUNA2000-213KTL-H0 Smart Power Control System User Manual 8 Device Maintenance Figure 8-19 Removing the Smart PCS Step 5 Install the new Smart PCS. For details, see Installation. Step 6 Connect the PE cable, DC power cables, AC power cables, and communications cables in sequence.
  • Page 97: Disposing Of The Smart Pcs

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 8 Device Maintenance Step 5 The settings of Grid Parameters, Protection Parameters, Feature Parameters, Power Adjustment, and Power Baseline of the new device must be synchronized from other devices. This section uses Grid Parameters settings as an example to describe how to synchronize data.
  • Page 98: Technical Specifications

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 9 Technical Specifications Technical Specifications Efficiency Item LUNA2000-213KTL-H0 Maximum efficiency 99.01% DC Side Item LUNA2000-213KTL-H0 Number of DC routes Maximum DC voltage 1500 V Maximum DC current ● 218.5 A (long term) ● 238 A (1 minute)
  • Page 99: General Specifications

    LUNA2000-213KTL-H0 Smart Power Control System User Manual 9 Technical Specifications Item LUNA2000-213KTL-H0 Maximum AC power ● 236.4 kW (long term) ● 257.7 kW (1 minute) Rated output current 153.7 A Maximum output current ● 170.6 A (long term) ● 186 A (1 minute)
  • Page 100 LUNA2000-213KTL-H0 Smart Power Control System User Manual 9 Technical Specifications Item LUNA2000-213KTL-H0 Operating temperature –25°C to +60°C (derated above +40°C) Cooling mode Smart air cooling Typical value: 75 dB Noise Maximum operating altitude 4700 m Relative humidity 0%–100% RH (non-condensing)
  • Page 101: A Crimping An Ot Or Dt Terminal

    LUNA2000-213KTL-H0 Smart Power Control System User Manual A Crimping an OT or DT Terminal Crimping an OT or DT Terminal Requirements on an OT or DT Terminal ● If a copper cable is used, use copper wiring terminals. ● If a copper-clad aluminum cable is used, use copper wiring terminals.
  • Page 102 LUNA2000-213KTL-H0 Smart Power Control System User Manual A Crimping an OT or DT Terminal Figure A-1 Requirements on an OT or DT terminal Crimping an OT or DT Terminal NO TICE ● Avoid scratching the core wire when stripping a cable.
  • Page 103 LUNA2000-213KTL-H0 Smart Power Control System User Manual A Crimping an OT or DT Terminal Figure A-2 Crimping an OT terminal (1) Cable (2) Core wire (3) Heat shrink tubing (4) OT terminal (5) Hydraulic pliers (6) Heat gun Figure A-3 Crimping a DT terminal...
  • Page 104 LUNA2000-213KTL-H0 Smart Power Control System User Manual A Crimping an OT or DT Terminal Figure A-4 Specifications of the crimped M12 OT/DT terminal Issue 04 (2024-12-30) Copyright © Huawei Technologies Co., Ltd.
  • Page 105: Grid Codes

    LUNA2000-213KTL-H0 Smart Power Control System User Manual B Grid Codes Grid Codes NO TICE If the actual grid parameters exceed the allowed ranges of the local standard grid parameters, the Company shall not be liable for any resulting device damage.
  • Page 106 LUNA2000-213KTL-H0 Smart Power Control System User Manual B Grid Codes Grid Code Description DUBAI-MV800 Dubai power grid SAUDI-MV800 Saudi Arabia power grid EN50549-MV800 Ireland power grid Northern Ireland-MV800 Northern Ireland power grid IEC 61727-MV800-60HZ General power grid Pakistan-MV800 Pakistan power grid...
  • Page 107 LUNA2000-213KTL-H0 Smart Power Control System User Manual B Grid Codes Grid Code Description Mauritius-MV800 Mauritius medium-voltage power grid Oman-PDO-MV800 Oman PDO medium-voltage power grid TAI-MEA-MV800 Thailand medium-voltage power grid PORTUGAL-MV800 Portugal medium-voltage power grid C10/11-MV800 Belgium medium-voltage power grid G99-TYPEB-HV-MV800...
  • Page 108 LUNA2000-213KTL-H0 Smart Power Control System User Manual B Grid Codes Grid Code Description FINLAND-EN50549-MV800 Finland power grid EN50549-SE-MV800 Sweden power grid CEPM-MV800 Dominican Republic medium-voltage power grid SA-BESF-L-MV800 South Africa BESF-L medium-voltage power grid SA-BESF-H-MV800 South Africa BESF-H medium-voltage power grid...
  • Page 109: C Resetting A Password

    LUNA2000-213KTL-H0 Smart Power Control System User Manual C Resetting a Password Resetting a Password Step 1 On the Monitoring page of the SmartLogger, choose the Smart PCS for which you need to reset the password, choose Running Param. > Feature Parameters, and set Safe mode to Enter.
  • Page 110: D Certificate Management And Maintenance

    Huawei's initial certificates are used only in the deployment phase, for establishing initial security channels between devices and the customer's network. Huawei does not promise or guarantee the security of the initial certificates. Customers shall bear consequences of all security risks and security incidents arising from using Huawei's initial certificates as service certificates.
  • Page 111: E How Do I Repair Paint Damage

    LUNA2000-213KTL-H0 Smart Power Control System User Manual E How Do I Repair Paint Damage? How Do I Repair Paint Damage? E.1 Repairing Paint Damage for Devices Prerequisites ● Do not apply paint in bad weather, such as rain, snow, strong wind, and sandstorm, when there is no shelter outdoors.
  • Page 112 LUNA2000-213KTL-H0 Smart Power Control System User Manual E How Do I Repair Paint Damage? Table E-1 Paint repair description Paint Damage Tool and Procedure Description Material Slight scratch Spray paint or Steps 1, 2, and 4 1. The color (base material...
  • Page 113 LUNA2000-213KTL-H0 Smart Power Control System User Manual E How Do I Repair Paint Damage? Table E-2 Paint requirements Item Requirement Primer thickness 120 μm Top coat thickness 60 μm Primer type Epoxy micaceous iron oxide paint Top coat type RAL 9003 and RAL 7035 polyurethane...
  • Page 114 LUNA2000-213KTL-H0 Smart Power Control System User Manual E How Do I Repair Paint Damage? NO TICE – If the base material is exposed in the area to be repaired, apply epoxy micaceous iron oxide primer, wait until the paint has dried, and then apply polyurethane top coat.
  • Page 115: Repairing Paint Damage For Mounting Brackets

    LUNA2000-213KTL-H0 Smart Power Control System User Manual E How Do I Repair Paint Damage? NO TE – The color of the repainted area must be consistent with that of the surrounding area. Use a colorimeter to measure the color difference (ΔE), which shall be less than or equal to 3.
  • Page 116 LUNA2000-213KTL-H0 Smart Power Control System User Manual E How Do I Repair Paint Damage? Table E-3 Paint repair description Paint Damage Tool and Procedure Description Material Slight scratch Spray paint or Steps 1, 2, 4, and 1. The color (steel base...
  • Page 117 LUNA2000-213KTL-H0 Smart Power Control System User Manual E How Do I Repair Paint Damage? Figure E-4 Polishing a damaged area using sandpaper Step 2 Dip a piece of cotton cloth into anhydrous alcohol and wipe the polished or damaged area to remove the dirt and dust. Then wipe off the anhydrous alcohol...
  • Page 118 LUNA2000-213KTL-H0 Smart Power Control System User Manual E How Do I Repair Paint Damage? Figure E-6 Repainting a damaged area Step 5 Wait for 30 minutes and check whether the painting meets the requirements. NO TE ● The color of the repainted area must be consistent with that of the surrounding area.
  • Page 119: Contact Information

    LUNA2000-213KTL-H0 Smart Power Control System User Manual F Contact Information Contact Information If you have any questions about this product, please contact us. https://digitalpower.huawei.com Path: About Us > Contact Us > Service Hotlines To ensure faster and better services, we kindly request your assistance in providing the following information: ●...
  • Page 120 LUNA2000-213KTL-H0 Smart Power Control System User Manual F Contact Information NO TE EU Representative Information: Huawei Technologies Hungary Kft. Add.: HU-1133 Budapest, Váci út 116-118., 1. Building, 6. floor. Email: hungary.reception@huawei.com Issue 04 (2024-12-30) Copyright © Huawei Technologies Co., Ltd.
  • Page 121: G Digital Power Customer Service

    LUNA2000-213KTL-H0 Smart Power Control System User Manual G Digital Power Customer Service Digital Power Customer Service https://digitalpower.huawei.com/robotchat/ Issue 04 (2024-12-30) Copyright © Huawei Technologies Co., Ltd.
  • Page 122: Acronyms And Abbreviations

    LUNA2000-213KTL-H0 Smart Power Control System User Manual H Acronyms and Abbreviations Acronyms and Abbreviations communication Fast Ethernet light emitting diode Smart PCS Smart Power Control System WLAN wireless local area network Issue 04 (2024-12-30) Copyright © Huawei Technologies Co., Ltd.

Table of Contents

Save PDF