PEN100 Unit Installation Instructions 1. Check using the Parts List that none of the components are missing. 2. Plan the final position of the play equipment ensuring there is sufficient space. 3. Sort and identify parts before assembly. 4. Excavate the foundation holes in accordance with the plan. Ensuring Curved post holes are levelled and chocked in at the bottom of the holes.
Page 3
PEN100 Unit Parts List Pen002 x11 Pen003 x1 Pen004 x2 Pen005 x1 Pen006 x2 (Slide Framework) Pen007 x4 Rev 00 Page 3...
Page 4
PEN100 Unit Parts List Pen008 x1 Pen009 x1 Pen010 x1 Pen013 x1 Pen014 x1 Rev 00 Page 4...
Page 5
PEN100 Unit Parts List Pen017 x1 Pen015 x1 Pen018 x1 Pen019 x1 Pen021 x2 Pen022 x2 Pen016 x1 Pen020 x1 Rev 00 Page 5...
Page 6
PEN100 Unit Parts List Pen023 x1 Pen026 x1 Pen038 x1 Pen029 x1 Pen024 x1 Pen027 x1 Pen031 x1 Pen028 x1 Rev 00 Page 6...
Page 12
PEN100 Installation Steps Guidance PEN002 PEN037 PEN002 PEN008 PEN007 PEN007 PEN002 PEN006 Assemble on the floor in preperation before tilting unit into the holes. Large Slide side for reference. Note: Ensure all holes are levelled to eachother and something solid is at the bottom of the hole before lifting.
Page 13
PEN100 Installation Steps Guidance Large Slide side for reference. Start to add the rest of the legs using the framework to brace it. Large Slide side for reference. Once all 5 Legs are up, remove the support stantion and continue building up the frame- work and platforms as per the layouts on Page 8.
Page 14
PEN100 Net Assemblies PEN013 WSR040 M10 Plain Washer FIX155 M10 x 30mm Security Screw MCS373 M10 x 120mm CSK Bolt PEN016 Rev 00 Page 14...
Page 15
PEN100 Installation Steps Guidance PEN019 1. Lift PEN017 up and out. 2. Slot PEN019 into the slots in Deck (PEN017) PEN017 3. Finally position Deck (PEN017) back onto the framework. Large Slide side for reference. Finally, add all panelling and metalwork activities.
Page 16
PEN100 Installation Steps Guidance Front View Right View Back View Left View Rev 00 Page 16...
PEN100 Panel Assembly General Panels are attached to General Panels are attached to framework using M10 x 35mm framework using M10 x 35mm CSK Bolts unless specified. CSK Bolts unless specified. MCS321 M10 x 35mm CSK Bolt Hand Hold Fixings: Hand Hold Fixings: MCS335 DZS005...
Page 18
PEN100 Plastic Slides Assembly 1. Ensure the slide opening is 1. Ensure the slide opening is in line with the deck platform in line with the deck platform for a smooth transition for the for a smooth transition for the 2.
Page 19
PEN100 Plastic Slides Assembly When assembling slide sections, When assembling slide sections, Mounting the Slide Supports: Mounting the Slide Supports: start from the top and work down start from the top and work down the slide. the slide. 2.4m Slide Support Positions: 2.4m Slide Support Positions: 1.6m Slide Support Position: 1.6m Slide Support Position:...
PEN100 Unit Maintenance Instructions NOTE The warranty is invalidated if these instructions are not followed. All wood needs annual inspection and retreatment where required. Recommended Regular Inspection and Maintenance Interval Days Check stability of structure, tighten connections if required. Check all uprights at ground level for corrosion and/or rot. Replace any defective parts.