TROUBLESHOOTING HANDLING

8
Troubleshooting handling
8.1

Troubleshooting

This section contains information and procedures pertaining to the
remedying of potential problems with the inverter.
To carry out troubleshooting, proceed as follows:
Check the warnings, error messages or error codes displayed on the
screen of the inverter.
If no error information is displayed on the screen, check whether the
following requirements have been fulfilled:
Has the inverter been set up in a clean, dry, well-ventilated area?
Is the DC switch set to ON?
Are the cables sufficiently dimensioned and short enough?
Are the input connections, output connections and the wiring all in good
condition?
Are the configuration settings for the relevant installation correct?
Are the display field and the communication cables correctly connected
and undamaged?
Follow the steps below to view recorded problems: Press "Back" to enter
the main menu in the normal interface. In the interface screen select "Event
List", then press "OK" to enter events.