Page 1
ATESS HPS20000TL-US/HPS30000TL-US Shenzhen Atess Power Technology Co.,Ltd 3rd floor, building 9, Henglong industrial park, the fourth industrial zone of Shuitian community, Baoan district, Shenzhen, China Hybrid energy system User Manual + 86 755 2998 8492 info@atesspower.com www.atesspower.com...
Caution,risk of electric shock All relative operations must b e p r o c e e d e d b y t h e Attention that needs to be paid when operating and maintaining ATESS professional electricians. HPS20000TL-US/HPS30000TL-US T h e r e w i l l b e r e s i d u a l...
If > Warranty service for the inverter does not contain module maintenance. necessary, you can seek help from ATESS Customer Service department. > Permission from the local utility company is required before installing the Energy Storage system and only professional personnel are qualified for the operation.
Function and safety parameters discharged. Don't change the parameters of the inverter without authorization from the local utility and ATESS Energy Technology Co., Ltd. Otherwise, it might lead to injury or equipment damage and the warranty of the inverter will be voided.
Product description 3.1 Energy Storage system 3.3 Product specification ATESS HPS20000TL-US/HPS30000TL-US hybrid inverter is designed for energy 3.3.1 Input parameter storage system, it converts DC current generated by battery bank into AC current Inverter model HPS2 00TL-US and feed into the load/grid, also it can take power from solar inverter or grid to...
3.3.3 Important notes Name Description Note 1:usage restrictions Display Inverter setting, browsing and operation A.if the load connecting to the inverter is impact load, HPS20000TL- status display US/HPS30000TL-US can only supply power to 4P/6P impact load at most such as 4P/6P motor. Cable inlet and outlet For input and output power cable conneciton...
LOAD Communication port DC/AC breaker HPS20000TL-US/HPS30000TL-US don't have AC and DC switches or load switches, customers need to add their own switches, or buy our company to design and produce switch boxes. The AC main switch can be used to disconnect the AC interface of the inverter from the grid.
Page 9
3.5 Working mode 3.5.3 On-grid backup priority mode (1) Grid supplies power to load and charges battery when PV power insufficient. HPS20000TL-US/HPS30000TL-US is designed with flexible working modes: (2)When the back-flow-prevention works, PV power can meet battery charge and load power.
3.5.5 On/Off-gird switch Operation logic: When grid power on, HPS can switch into on-grid mode If there is a long time before installation or operation, the ATESS HPS20000TL- US/HPS30000TL-US should be stored appropriately. automatically; when grid power off, HPS can switch into off-grid mode automatically.
Products installation 3.8 Packaging information 4.1 Installation condition requirements To ensure normal operation of the machine, the installation environment is required as follows: Quantity Name Unit A. The wall for mounting HPS should be solid and able to bear the weight of HPS in the long term.
4.2 Installation environment 4.3 Space requirement Although HPS is with IP54 protection level, it is not recommended to install it under When installing HPS, reasonable distance should be kept for maintenance and direct sun or direct rain/snow to ensure long term performance, below installation ventilation, please refer to below figure: environment for reference: To avoid inverter life span decrease, it is recommended to install shading shield on...
4.4 Tools and spare parts required for whole machine installation Steps: A:Please drill the hole according to the hole mask. Tools and spare parts required for installation is as follows: B:Please install the expansion bolt as shown. • Hoisting crane, forklift or fork lift truck (with the capacity for bearing the weight of C:Please install the wall hanger as shown in the picture.
CAUTION! Caution, risk of danger HPS30000TL-US HPS20000TL-US Model 1. HPS20000TL-US/HPS30000TL-US of AC and DC, do not have switches or circuit breakers, customers need to add their own Grid Voltage Limit 108V-132V/216-264V 188-228V switches, or buy our company design and production switch box.
4.6.4 AC side wiring Step 1: Cut off the distribution circuit breaker at the DC side, and ensure that no voltage on the wire at DC side. Step 2: Confirm the battery positive and negative voltage within range with a CAUTION! multimeter.
4.6.5 Earthing Rs485 communication line uses terminal blocks at both ends, and RS485 communication lines are made by parallel connection of terminals at both ends. The length should not exceed 1000 meters. As shown in Figure 4-7-1-1. Inverter must be earthing well for safety; Please make sure of the connection between PE in power distribution cabinet and PE copper in the inverter good;...
Pilot operation Electrical Installation Inspection The chapter will introduce the procedure of pilot operation, including checking battery voltage, input and output connecting, other preparation working. Complete and firm grounding of inverter. 5.1 Relevant requirements Grid voltage matching the rated input voltage of inverter. Correct phase sequence of grid connection, and tightening torque meeting requirements.
Warning: CAUTION! • After manually shutting down, you must press the power button on When connecting the load,make sure that the three-phase of the load the LCD, otherwise cannot start automatically. is corresponding to the three-phase of the HPS, otherwise it will cause the motor to reverse.
Maintenance Table 6-1 ATESS HPS-TL LCD Menu After the LCD is powered on, go directly to the home page of the interface. At this time, wait for the internal initialization of the machine for about 1 minute(If there is no data refresh after more than 2 minutes, the serial communication between the LCD and the control board is faulty).
6.2.3 Switch on/off page Language Settings: Select language, currently it only supports Chinese, English (default language is Chinese). You can enter this page by clicking the [Switch on/off] button in any other interface. There are the on button, the off button. Used to select power on or off operation. After selecting, select [Yes] / [No] in the pop-up sub-window to confirm.
6.2.6 Operation data You can enter this page by clicking the [Run Data] button below any other interface. This page mainly displays the current energy storage power generation parameters and real-time data including grid voltage, grid frequency, grid current, DC input voltage, DC input current, chassis temperature and total power generation time, etc.
6.3.3 Inverter status Warning: Description Do not use a gas pump to clean the fan, as this may cause damage to the fan. wait Fan cleaning or replacement: check 1. Before cleaning or replacing the fan, please make sure that the DC side and AC Grid mode side of the inverter have been disconnected.
Table 7-2. the contract shall prevail. During the warranty period, ATESS products shall promptly present the invoice and date of purchase of the products to ATESS Service personnel during maintenance. At the same time on the product the nameplate logo should be clearly visible, otherwise it will not be repaired.
Page 27
Warranty condition ATESS will repair or replace the product free of charge during the warranty period; the faulty machine after replacement shall be owned by ATESS; the customer shall reserve a certain amount of time for ATESS to repair the faulty machine.
Need help?
Do you have a question about the HPS20000TL-US and is the answer not in the manual?