Page 1
ATESS HPS15000TL/HPS20000TL Shenzhen Atess Power Technology Co.,Ltd Growatt ATESS Indudtrial Park No 23 Zhulongtian Road Shuitian Community Shiyan Street Baoan District Shenzhen Chian Hybrid energy system User Manual + 86 755 2998 8492 info@atesspower.com www.atesspower.com Revised date: 2024.01.05...
Caution,risk of electric shock All relative operations must b e p r o c e e d e d b y t h e Attention that needs to be paid when operating and maintaining ATESS professional electricians. HPS15000TL/HPS20000TL T h e r e w i l l b e r e s i d u a l...
If > Warranty service for the inverter does not contain module maintenance. necessary, you can seek help from ATESS Customer Service department. > Permission from the local utility company is required before installing the Energy Storage system and only professional personnel are qualified for the operation.
Function and safety parameters discharged. Don't change the parameters of the inverter without authorization from the local utility and ATESS Energy Technology Co., Ltd. Otherwise, it might lead to injury or equipment damage and the warranty of the inverter will be voided.
Product description 3.1 Energy Storage system 3.3.2 Output parameter ATESS HPS15000TL/HPS20000TL hybrid inverter is designed for energy storage system, it converts DC current generated by battery bank into AC current and feed HPS20000TL Energy storage controller model HPS15000TL into the load/grid, also it can take power from solar inverter or grid to charge battery .
3.4 The layout of the main parts Cable inlet and outlet 3.4.1 External layout Figure 3-4-1-3 Inverter cable inlet and outlet Description Port SWITCH I PV DC switch BAT cable gland Cable gland for LOAD output LOAD Cable gland for GRID input GRID Communication port Figure 3-4-1-1 Inverter appearance...
3.4.2 Inner component layout 3.5.2 Grid-connected load priority mode ㈠ PV POWER > LOAD POWER DC/AC breaker HPS15000TL/HPS20000TL doesn’t have AC and DC switches or load switches, customers need to add their own switches, or buy our company to design and DC/DC DC/AC LOAD produce switch boxes.
AC/DC contactor and enters into the Permanent fault mode, so as to ensure the ㈠ PV POWER > BAT POWER safety of the system. For example: inverter module failure etc. please contact your local dealer or ATESS directly when inverter enters permanent fault mode, repairmen DC/DC DC/AC LOAD on site is not allowed without authorization of ATESS.
> Retain the desiccant in the packaging. B. Installation space should be sufficient to cover HPS dimension, HPS dimension > The ATESS HPS15000TL/HPS20000TL can only be stored when it is stopped and and installation gap please see below photo: all the doors are closed in a dry room to protect the internal circuits against dust and C.
4.2 Installation environment 4.3 Space requirement Although HPS is with IP54 protection level, it is not recommended to install it under When installing HPS, reasonable distance should be kept for maintenance and direct sun or direct rain/snow to ensure long term performance, below installation ventilation, please refer to below figure: environment for reference: To avoid inverter life span decrease, it is recommended to install shading shield on...
4.4 Tools for installation Steps: A:Please drill the hole according to the hole mask. Tools and spare parts required for installation is as follows: B:Please install the expansion bolt as shown. • Hoisting crane, forklift or fork lift truck (with the capacity for bearing the weight of C:Please install the wall hanger as shown in the picture.
4.6 Electrical installation 4.6.1 Electrical Parallel Wiring Diagrams 1.Wiring diagram of a single HPS 2.Parallel wiring 3.Parallel wiring diagram of a HPSwith batteries diagram of connected in parallel independent battery Recommended switch for HPS15000TL/HPS20000TL DC breaker:100A/1000V AC breaker:63A/400V...
Page 14
CAUTION! Caution, risk of danger HPS15000TL/HPS20000TL Model 1. HPS15000TL/HPS20000TL of AC and DC, do not have switches or circuit breakers, customers need to add their own switches, or buy our 360V~440V Grid Voltage Limit company design and production switch box.
Page 15
4.6.5 AC side wiring Step 1: Cut off the distribution circuit breaker at the DC side, and ensure that no voltage on the wire at DC side. Step 2: Confirm the battery positive and negative voltage within range with a CAUTION! multimeter.
4.6.6 Earthing Rs485 communication line uses terminal blocks at both ends, and RS485 communication lines are made by parallel connection of terminals at both ends. The length should not exceed 1000 meters. As shown in Figure 4-7-1-1. Inverter must be earthing well for safety; Please make sure of the connection between PE in power distribution cabinet and PE copper in the inverter good;...
Pilot operation Electrical Installation Inspection The chapter will introduce the procedure of pilot operation, including checking battery voltage, input and output connecting, other preparation working. Complete and firm grounding of inverter. 5.1 Relevant requirements Grid voltage matching the rated input voltage of inverter. Correct phase sequence of grid connection, and tightening torque meeting requirements.
Warning: CAUTION! • After manually shutting down, you must press the power button on When connecting the load,make sure that the three-phase of the load the LCD, otherwise cannot start automatically. is corresponding to the three-phase of the HPS, otherwise it will cause the motor to reverse.
Communication station number 6.1 Introduction to touch screen Users can view the operation information of the energy storage controller on the LCD touch screen, as well as set the operating parameters of the energy storage controller. For ease of operation, the following is a distribution diagram of the LCD menu logic structure.
Page 20
6.2.2 Power On/Off 6.2.4 System settings Click the [Power on/off] button in any other interface to enter this page. In this page, the Language settings:Select the interface language under this page, currently only two main ones are: boot button, shutdown button. Used to select the power on or off languages, Chinese and English.
Page 21
This page is the battery parameter setting page, the battery is an important part of the Grid Power UP Limit: the upper limit value of grid power, the maximum value is 1.2 energy storage control system, and the battery parameters need to be carefully times the rated power.
Page 22
Information:The manufacturer, serial number, software and hardware version Max.Bypass Voltage: The upper limit of the grid voltage, beyond which it will be cut into information, and factory date information are displayed under this page, which only off-grid mode, which is set by 110% of the rated value. shows that it cannot be modified.
Page 23
Discharge Stop SOC, discharge stop voltage: Only in "load priority" and "peak Float Charge Volt Limit: the voltage value of the battery into the float state, when the period" of economic mode, when the cell voltage or SOC reaches the discharge cut-off battery cell voltage is greater than (float voltage - float charge current limiting point), the voltage or SOC, the battery stops discharging.
Page 24
GFDI Ground Select: Reserved. Grid PV Charge Enable: when set to 1, the grid and PV can charge the battery at the same time, preferably supplied by PV, supplemented by the grid when insufficient; When set to 0, the grid and PV cannot charge the battery at the same time. Preferentially supplied by PV, PV will only be charged by the grid when there is no power.
Page 25
Calibration settings Forced Charge Enable: Set to 1 when using batteries produced by ATESS, otherwise set to 0. The parameters on this page are important parameters and factory preset parameters, Shinemaster Failure Flag: Reserved. please do not modify them without the consent of relevant personnel. The Company is not responsible for any consequences.
Factory Settings Alarm information: The fault reported by the energy storage inverter is displayed, the fault time is displayed on the left, and the corresponding fault name is displayed on the The parameters on this page are important parameters and factory preset parameters, right.
6.3.3 Inverter status Warning: Do not use a gas pump to clean the fan, as this may cause damage to the fan. Description Fan cleaning or replacement: wait 1. Before cleaning or replacing the fan, please make sure that the DC side and AC check side of the inverter have been disconnected.
Table 7-2. the contract shall prevail. During the warranty period, ATESS products shall promptly present the invoice and date of purchase of the products to ATESS Service personnel during maintenance. At the same time on the product the nameplate logo should be clearly visible, otherwise it will not be repaired.
Page 32
Warranty condition ATESS will repair or replace the product free of charge during the warranty period; the faulty machine after replacement shall be owned by ATESS; the customer shall reserve a certain amount of time for ATESS to repair the faulty machine.
Need help?
Do you have a question about the HPS15000TL and is the answer not in the manual?
Questions and answers