Installation Guide Product introduction Eaton Green Motion Fleet Pro replacement J1172 EV connector and 25-foot cord. For use with Eaton Green Motion Fleet Pro, 80 A (GMEV80CME1-WC, GMEV80CMC1-WC). Product Family Description Green Motion Fleet Pro EVCCJ1772-V80 Replacement J1772 EV connector and 25-foot cord, 80 A...
YOUR ELECTRIC UTILITY TO DISCONNECT POWER TO AN EXISTING LOADCENTER. THE LINE SIDE OF THE MAIN BREAKER IS ENERGIZED UNLESS POWER IS DISCONNECTED UPSTREAM. EATON WILL NOT ASSUME RESPONSIBILITY FOR PROPERTY DAMAGE OR PERSONAL INJURY RESULTING FROM MISUSE OF THE INFORMATION IN THIS PUBLICATION.
. This equipment should be located at least 18 inches (460 mm) above the floor . 15” min 15” min 10” max 48” max GREEN MOTION FLEET PRO CORD REPLACEMENT www.eaton.com 15” min...
Green Motion Fleet Pro cord replacement Ensure the power is turned OFF before starting installation. CAUTION: Disconnect the old EV charging cable STEP A-1 Open the cabinet with the key (1) . Disconnect CS and CP signal wires and unscrew the L1, L2, and ground wire .
. Close and lock the cabinet (1) . Torque specs • L1 and L2: 21 .7 lbf-in • GND: 13 .9 lbf-in Ground Installation is complete. It is safe to restore power. GREEN MOTION FLEET PRO CORD REPLACEMENT www.eaton.com...