5.7.8
Vertical roof terminal and vertical double pipe flue system
Unit category: C33
CAUTION
If the vertical combi feedthrough cannot be applied, the air
supply and combustion gas outlet must be carried out
separately.
Vertical combi feedthrough
Permitted pipe length
For parallel: Air supply and combustion gas outlet together, excluding the length of
the combi feedthrough.
For concentric: total pipe length, excluding the length of the combi feedthrough.
RKOMB22AAV1H
RKOMB28AAV1H
RKOMB33AAV1H
Combustion gas outlet and air supply pipe
For assembly, see par. 5.6.5 General assembly.
Assembly vertical roof terminal
1.
Fit a vertical feed-through panel with scale at the location of the outlet on a
sloped roof.
A flat roof requires an adhesive panel for a Ø126 mm pipe.
2.
Disassemble the manifold from the combi feedthrough.
3.
Slide the combi feedthrough from outside to inside:
In case of a sloped roof, through the vertical feed-through panel with scale.
In case of a flat roof, through the adhesive panel.
4.
In case of a parallel connection, fit the manifold of the combi feedthrough and
secure it with a sheet metal screw or pop rivet.
ROTEX Heating Systems GmbH
Parallel
Concentric
Concentric
60/100
80/125
100 m
11 m
85 m
10 m
80 m
10 m
29 m
29 m
29 m
28