Conversion from A-B to A-C
2. Remove phase-link and strap in position B.
3. Install strap in position C.
4. Do not use phase-link and insulation sheet
5. Tighten all connections to 170 in-lbf.
Conversion from B-C to A-B
2. Remove strap in position C.
3. Switch position of phase-link and insulation sheet
from position A-B to position B-C
4. Install strap in position A.
5. Tighten all connections to 170 in-lbf.
Conversion from A-B to B-C
2. Remove strap in position A.
3. Switch position of phase-link and insulation sheet
From position B-C to position A-B
4. Install strap in position C.
5. Tighten all connections to 170 in-lbf.
Lever-Bypass 320A Meter-sockets
Parts included with the product:
1. Turn off power supplying the equipment
Conversion from A-C to B-C
2. Remove meter-barrier at location to convert
3. Remove A-Phase strap
4. Install phase-link, insulation, and 3/8 bolt in position A-B.
5. Install B-phase strap in position B
6. Tighten all connections to 170 in-lbf.
7. Re-Install meter-barrier
Conversion from A-C to A-B
2. Remove meter-barrier at location to convert
3. Remove C-phase strap
4. Install phase-link, insulation, and 3/8 bolt in position B-C.
5. Install B-phase strap in position B
6. Tighten all connections to 170 in-lbf.
7. Re-install meter-barrier