Usage Scenarios - Keithley 4210-MMPC-S Quick Start Manual

Multi-measurement prober cable kit

Advertisement

Model 4210 MMPC-S Quick Start Guide

Usage scenarios

I-V testing:
2-pin I-V setup
NOTE
The setup for 2-pin I-V testing requires two prober cable kits.
With two Model 4200-SMUs connected to the prober bulkhead, use the fundamental setup shown in Figure 10 to
perform 2-pin I-V testing. Figure 3 shows the SMU connections to the outside of the bulkhead.
Figure 10: Test setup for 2-pin I-V testing
I-V testing: 4-pin I-V setup
With four Model 4200-SMUs connected to the prober bulkhead, use the setup shown in Figure 11 to perform 4-pin
I-V testing. Figure 3 shows two SMUs connected to one of the bulkhead connection panels. Connect two additional
SMUs to the other bulkhead connection panel.
NOTE
The setup for 4-pin I-V testing requires four prober cable kits.