Evaporator Coil; Evaporator Coil Metering Devices; Thermostatic Expansion Valve (Txv); Txv Operation - Carrier 48FC M20 Series Service And Maintenance Instructions

Single package rooftop gas heat/electric cooling unit with puron (r-410a) refrigerant 17.5-27.5 nominal tons
Table of Contents

Advertisement

Totaline Environmentally Balanced Coil Cleaner Application
Equipment
2-1/2 gallon garden sprayer
Water rinse with low velocity spray nozzle
Totaline Environmentally Balanced Coil Cleaner Application
Instructions
1.
Proper eye protection such as safety glasses is recommended
during mixing and application.
2.
Remove all surface loaded fibers and dirt with a vacuum
cleaner as described above.
3.
Thoroughly wet finned surfaces with clean water and a low
velocity garden hose, being careful not to bend fins.
4.
Mix Totaline environmentally balanced coil cleaner in a
2-1/2 gallon garden sprayer according to the instructions
included with the cleaner. The optimum solution tempera-
ture is 100°F.
NOTE: Do NOT USE water in excess of 130°F, as the enzymatic
activity will be destroyed.
5.
Thoroughly apply Totaline environmentally balanced coil
cleaner solution to all coil surfaces including finned area, tube
sheets and coil headers.
6.
Hold garden sprayer nozzle close to finned areas and apply
cleaner with a vertical, up-and-down motion. Avoid spraying
in horizontal pattern to minimize potential for fin damage.
7.
Ensure cleaner thoroughly penetrates deep into finned areas.
Interior and exterior finned areas must be thoroughly cleaned.
Finned surfaces should remain wet with cleaning solution for
10 minutes. Ensure surfaces are not allowed to dry before
rinsing. Reapply cleaner as needed to ensure 10-minute satu-
ration is achieved.
8.
Thoroughly rinse all surfaces with low velocity clean water
using downward rinsing motion of water spray nozzle. Pro-
tect fins from damage from the spray nozzle.

Evaporator Coil

Cleaning the Evaporator Coil
1.
Turn unit power off. Install lockout tag. Remove evapora-
tor coil access panel.
2.
If economizer or two-position damper is installed, remove
economizer by disconnecting Molex
mounting screws.
3.
Slide filters out of unit.
4.
Clean coil using a commercial coil cleaner or dishwasher
detergent in a pressurized spray canister. Wash both sides
of coil and flush with clean water. For best results, back-
flush toward return-air section to remove foreign material.
Flush condensate pan after completion.
5.
Reinstall economizer and filters.
6.
Reconnect wiring.
7.
Replace access panels.

Evaporator Coil Metering Devices

48FC 20-30 units with or without the Humidi-MiZer option use a
TXV-distributer system.
1. Third-party trademarks and logos are the property of their respective
owners.
plug and removing
®1
15

THERMOSTATIC EXPANSION VALVE (TXV)

The TXV is a bi-flow, bleed port expansion valve with an external
equalizer. The TXVs are specifically designed to operate with
Puron
refrigerant. Use only factory-authorized TXVs.
®

TXV Operation

The TXV is a metering device that is used in air conditioning and
heat pump systems to adjust to the changing load conditions by
maintaining a preset superheat temperature at the outlet of the
evaporator coil.
The volume of refrigerant metered through the valve seat is de-
pendent upon the following:
1.
Superheat temperature is sensed by cap tube sensing bulb
on suction tube at outlet of evaporator coil. This tempera-
ture is converted into pressure by refrigerant in the bulb
pushing downward on the diaphragm, which opens the
valve using the push rods.
2.
The suction pressure at the outlet of the evaporator coil is
transferred through the external equalizer tube to the
underside of the diaphragm.
3.
The pin is spring loaded, which exerts pressure on the
underside of the diaphragm. Therefore, the bulb pressure
works against the spring pressure and evaporator suction
pressure to open the valve. If the load increases, the tem-
perature increases at the bulb, which increases the pressure
on the top side of the diaphragm. This opens the valve and
increases the flow of refrigerant. The increased refrigerant
flow causes the leaving evaporator temperature to decrease.
This lowers the pressure on the diaphragm and closes the
pin. The refrigerant flow is effectively stabilized to the load
demand with negligible change in superheat.

Replacing TXV

1.
Recover refrigerant.
2.
Remove TXV support clamp using a 5/l6-in. nut driver.
3.
Remove TXV using a wrench and an additional wrench on
connections to prevent damage to tubing.
4.
Remove equalizer tube from suction line of coil. Use file
or tubing cutter to cut brazed equalizer line approximately
2 inches above suction tube.
5.
Remove bulb from vapor tube inside cabinet.
6.
Install the new TXV using a wrench and an additional
wrench on connections to prevent damage to tubing while
attaching TXV to distributor.
7.
Attach the equalizer tube to the suction line. If the coil has
a mechanical connection, then use a wrench and an addi-
tional wrench on connections to prevent damage. If the
coil has a brazed connection, use a file or a tubing cutter to
remove the mechanical flare nut from the equalizer line.
Then use a new coupling to braze the equalizer line to the
stub (previous equalizer line) in suction line.
8.
Attach TXV bulb in the same location where the original
(in the sensing bulb indent) was when it was removed,
using the supplied bulb clamps. See Fig. 21.
9.
Route equalizer tube through suction connection opening
(large hole) in fitting panel and install fitting panel in place.
10. Sweat the inlet of TXV marked "IN" to the liquid line.
Avoid excessive heat which could damage the TXV valve.
Use quenching cloth when applying heat anywhere on TXV.