6.6. Method for opening the sliding plate

The sliding plate should be moved to the open position in the following
regions to minimize temperature rise in the main control box: CA,
NV, AZ, NM, OK, TX, AR, LA, MS, AL, TN, GA, NC, SC, FL and Latin
America.
1 Remove the left screw (1 pc.) and loosen the right screw (1 pc.).
SLIDING PLATE
2 Move the sliding plate to the right and set the arrow to "OPEN".
3 Reinstall the left screw and tighten both the left and right screws.
NOTE
Failure to follow the above instructions could lead to premature com-
ponent failure.
9
SCREW

7. Refrigerant pipe size and allowable pipe length

7.1. General information

NOTE
The refrigerant R410A requires strict cautions for keeping the system
clean, dry and tight.
• Clean and dry: foreign materials (including mineral oils or moisture)
should be prevented from getting mixed into the system.
• Tight: R410A does not contain any chlorine, does not destroy
the ozone layer, and does not reduce earth's protection against
harmful ultraviolet radiation. R410A can contribute slightly to the
greenhouse effect if it is released. Therefore we should take special
attention to check the tightness of the installation.

7.2. Selection of piping material

NOTE
Piping and other pressure containing parts shall comply with the appli-
cable legislation and shall be suitable for refrigerant. Use phosphoric
acid deoxidized seamless copper for refrigerant.
NOTE
• All field piping must be installed by a licensed refrigeration techni-
cian and must comply with relevant local and national regulations.
• After piping work is complete, do not under any circumstances open
the stop valve until 9. Field wiring on page 18 and 12. Checking of
device and installation conditions on page 24 are complete.
• Do not use flux when brazing the refrigerant piping. Use the phos-
phor copper brazing filler metal (B-Cu93P-710/795 : ISO 3677)
which does not require flux. Flux has extremely negative effect on
refrigerant piping systems. For instance, if the chlorine based flux is
used, it will cause pipe corrosion or, in particular, if the flux contains
fluorine, it will damage the refrigerant oil.
• Use only pipes which are clean inside and outside and which do not
accumulate harmful sulfur, oxidants, dirt, cutting oils, moisture, or
other contamination. (Foreign materials inside pipes including oils
for fabrication must be 0.14 gr/10 ft. (30 mg/10 m) or less.)
• Use the following items for the refrigerant piping.
Material : Jointless phosphor-deoxidized copper pipe.
Size : See 7.3. Selection of piping size to determine the correct
size.
Thickness : Select a thickness for the refrigerant piping which
complies with national and local laws.
• For piping work, follow the maximum tolerated length, difference in
height, and length after a branch indicated in the 7.5. System piping
(length) limitations on page 11.
• Outdoor unit multi connection piping kit and refrigerant branch kit
(sold separately) are needed for connection of piping between
outdoor units (in case of multi system) and piping branches.
• Use only separately sold items selected specifically according to
the outdoor unit multi connection piping kit, the refrigerant branch kit
selection in the 7.4. Selection of refrigerant branch kits on page 11.