POWER FLUSH MONITORING FORM
Visual inspection of system water before power flush:
Clear
Test parameter
pH
Soluble iron (ppm)
Soluble copper (ppm)
Chloride (ppm)
Hardness
Inhibitor (ppm molybdate)
Mains water (ppm)
When checking dump water TDS from each radiator when dumping, note results below (ppm):
Radiator 1
Radiator 2
Radiator 3
Radiator 4
Radiator 5
Radiator 6
Radiator 7
Flushing chemical used:
POWERFLUSH FX2
Corrosion inhibitor used:
SYSTEMSAFE-DM
The undersigned has power flushed the system according to best industry practice and following procedures
detailed in code of practice BS7593
Name:
Date:
Issue: May 2023
Orange
Analysis results
Mains water
TDS (Total Dissolved Solids) readings
Radiator 8
Radiator 9
Radiator 10
Radiator 11
Radiator 12
Radiator 13
Radiator 14
HYPERFLUSH
Section B – Using the Clearflow pump
Dark brown
System water before
power flush
System water before flush (ppm)
Radiator 15
Radiator 15
Radiator 17
Radiator 18
Radiator 19
Radiator 20
Radiator 21
Signature:
Black
System water after
power flush
Page B.16