Assembly
9 Attach the cable (F) of the contact pressure
gauge (E) with a cable tie (H) to the pipe.
10 Insert the cable (F) into the cable clip (G).
11 Connect the cable (F) to the connection
terminal (D), see "Connection terminal
allocation plan" on page 27.
I
J
12 Connect the soldered inlet connection (J) to the
piping network.
13 Connect the soldered outlet connection (K) to
the piping network.
14 Only for pressure-reducing station 100 with
reserve supply:
Connect the reserve supply (I):
– Release the union nut at the ball valve.
– Remove the sealing ring.
– Connect the inlet screw connection to the
reserve supply.
15 Place system under operating pressure.
16 Slowly open all ball valves.
17 Test all connection points for leaks using a leak
detection agent.
18 Close all ball valves.
22
K
Instructions for use Air filter station 60/190 Pressure-reducing station 100/300
Pressure-reducing station 100/8 bar
A
1 Position the base plate (A) in accordance with
the requirements on site.
2 Mark the drill holes of the base plate (A) on the
wall.
3 Drill the holes.
4 Insert the wall anchors.
5 Screw the base plate (A) to the wall.
245