Water Connections; Connection Diagram - Trane LIFT 81-P Installation Operation & Maintenance

Water-cooled heat pumps with scroll compressors for hot water production at very high temperatures heating capacity 37-550 kw
Table of Contents

Advertisement

4 | Water connections

4. WATER CONNECTIONS
4.1

Connection diagram

User side
1
UNIT
Anti-vibration joint (recommended)
ANT
CV
Check valve
Flow switch (recommended)
FL
FTR
Mesh filter (mandatory)
MN
Water gauge
Circulating pump
MP
RI
Shut-off ball valve
RIC
Automatic water filling valve
Automatic air vent (mandatory)
SFA
ST
Inertial tank
Expansion vessel
VE
VSI
Safety valve (mandatory)
14
Source side
1
UNIT
Anti-vibration joint (recommended)
ANT
CV
Check valve
FL
Flow switch (recommended)
FTR
Mesh filter (mandatory)
MN
Water gauge
Circulating pump
MP
RI
Shut-off ball valve
RIC
Automatic water filling valve
Automatic air vent (mandatory)
SFA
ST
Inertial tank
Expansion vessel
VE
VSI
Safety valve (mandatory)
Some of the components in the diagram may already be
included in the unit with the hydronic kit. Those not included
must be provided by the installer.
Connection pipes must have a suitable diameter and be
supported so as not to impose their weight on the unit.
The units allow synergies to be created at plant level by offering
the possibility of recovering heat from industrial processes or to
be integrated with other technical systems that produce hot
water at medium temperature. Part of the energy produced can
be used as a heat source by the units to produce hot water at
high temperature.
4.1.1
Water filter
Water filters must always be installed on the machine inlet side.
Square mesh filters must be installed with:
- maximum side of 0,8 mm up to diameter DN80
- maximum side of 1,6 mm up to diameter DN150
The dimensions and the pressure drops must be adapted to the
installation.
Filters must be clean periodically.