Page 2
Responsible Refrigerant Practices! Trane believes that responsible refrigerant practices are important to the environment, our customers, and the air conditioning industry. All technicians who handle refrigerants must be certified. The Federal Clean Air Act (Section 608) sets forth the requirements for handling, reclaiming, recovering and recycling of certain refrigerants and the equipment that is used in these service procedures.
4. Store units in the normal UP orientation to maintain oil in the compressor. 5. Do not stack more than three units in total height for the WPWD/GSWD 2-ton through 6-ton configurations, and no more than two units high for the EXWA 20-ton configuration.
Units containing the Deluxe 24V con- trol design will incorporate a micro- processor-based control board. The Trane microprocessor board is factory wired to a terminal strip to provide all necessary terminals for field connec- tion. The deluxe board is equipped...
Table 1: Unit weights Shipping Shipping Size Weight Weight with pallet (lb) w/o pallet (lb) 1222 1156 Figure 1: Mechanical clearances Dimensions/Weights/ Clearance WARNING Improper Unit Lift! Test lift unit approximately 24 inches to verify proper center of gravity lift point. To avoid dropping of unit, reposition lifting point if unit is not level.
Installation General Installation Checks The checklist below is a summary of the steps required to successfully in- stall a unit. This checklist is intended to acquaint the installing personnel with procedures required in the installation process. It does not replace the de- tailed instructions called out in the ap- plicable sections of this manual.
Page 12
Cleaning and Flushing the Water Loop After the piping system is complete, the flexible hose connectors should be doubled back to complete the water circuit external to the unit (avoiding trash settle-out in the condenser). Fig- ure 4. An extra pipe may be necessary to connect the hose kits.
Page 13
See Figure 7. If the unit s contain a Trane loop pump module, shut-off valves are supplied by the manufacturer within the pump module assembly.
Page 14
Water Heater Hook-up (option) Instructions for connection from the desuperheater (option) water-in/out to the domestic hot water heater may be found in WSHPC-IN-4 or 72-9006-02. This water heater kit (Figure 8) ships in all units with the desuperheater op- tion. The kit is zip tied to the compres- sor base;...
Filling the Loop Pump Kit System Once the loop, pump module and unit are fully connected, the system will need to be filled with water or water/ antifreeze solution. See Page 14 for an- tifreeze/water mixture by volume. Fill both sides of the outside portion of the loop first via the pump module.
Field Installed Power Wiring Power wiring to the equipment must conform to National and Local Electric Codes (NEC) by a professional electri- cian. WARNING Live Electrical Components! During installation, testing, ser- vicing and troubleshooting of this product, it may be necessary to work with live electrical compo- nents.
Controls Using 24 VAC Before installing any wire, refer to the electrical access locations on the unit submittals located on pages 7 through Ensure that the AC control wiring be- tween the controls and the unit’s ter- mination point does not exceed three (3) ohms/conductor for the length of the run.
Page 18
Changing Freezestat or Low Pres- sure Cutout Switches (WPWD/GSWD models ONLY) Each unit has two factory installed low pressure cutout switches and one freezestat. Only one of the low pres- sure cutout switches is connected to the 24 volt control circuit, dependent on which freezestat is being used (i.e.
Pre-Start-up Checklist Before energizing the unit, the following system devices must be checked: ____ Is the high voltage power supply correct and in accordance with the nameplate ratings? ____ Is the field wiring and circuit protection the correct size? ____ Is the low voltage control circuit wiring correct per the unit wiring diagram? ____ Is the piping system clean/complete and correct? (A recommendation of all system flushing of debris from the water- to-refrigerant heat exchanger, along with air purging from the water-to-refrigerant heat exchanger be done in accor- dance with the Closed-Loop/Ground Source Heat Pump Systems Installation Guide).
Initial Unit Start-up Start-up with the system controls is included below: Note: Air Handlers should not be operated in the construction phase of dry walling. The air-to-refrigerant coil will foul, and the warranty will be void. 1.Set the system control to the desired mode of operation. 2.Set the control switch to fans and circulation pumps.
Page 23
38.1 53.6 30.5 50.5 53.6 14.7 Water Side Volume Gallons 0.238 0.455 0.455 1.121 1.121 1.121 Note: The EXWA 240 has two circuits. 4.576 Source Load Ft. Head Ft. Head Pressure Pressure 10.8 12.2 12.1 16.2 11.0 13.3 14.0 21.9 14.0...
Installing Contractor: Use this form to thoroughly check-out the system and units before and during start-up. (This form need not be returned to the factory unless requested during technical service support). Job Name: Model Number: Date: Serial Number: In order to minimize troubleshooting and costly system failures, complete the following checks and data entries before the system is put into full operation.
WSHP-SVX02A-EN Maintenance Preventive Maintenance Maintenance on the unit is simplified with the following preventive sugges- tions: WARNING Hazardous Voltage! Disconnect all electric power, in- cluding remote disconnects be- fore servicing. Follow proper lockout/tagout procedures to en- sure the power can not be inad- vertently energized.
Warranty Information Standard Warranty The standard water-source heat pump warranty is Trane’s parts-only warranty, running 12-months from star- tup, not to exceed 18-months from shipment. Extended Warranty The optional extended warranty is a second through fifth year warranty. The time starts at the end of standard 1-year coverage through the fifth year.
WSHP-SVX02A-EN Troubleshooting WARNING Hazardous Service Procedures! The maintenance and trouble shooting procedures recommend- ed in this section of the manual could result in exposure to electri- cal, mechanical or other potential safety hazards. Always refer to the safety warnings provided throughout this manual concern- ing these procedures.
Problem No response to any thermostat setting Unit short cycles Insufficient capacity High pressure switch open High head pressure Low suction pressure Low Pressure switch open Freezestat open Troubleshooting Checklist Heating Cooling Cause Main power off Defective control transformer Broken or loose connection Defective thermostat Transformer Thermostat or sensor improperly located...
Unit Wiring 2-ton through 6-Ton Equipment WSHP-SVX02A-EN...
Page 30
Unit Wiring 20-Ton Equipment WSHP-SVX02A-EN...
Page 31
An American Standard Company www.trane.com For more information, contact Since Trane has a policy of continuous product and data improvement and reserves the right to change your local district office or e-mail us at design and specifications without notice. comfort@trane.com...
Need help?
Do you have a question about the EXWA and is the answer not in the manual?
Questions and answers