Adding refrigerants in running condition
1 . Press the function key for adding refrigerant .
2 . After 30 minutes of operation, open the Charging Ports on low pressure side in Heat Pump .
3 . Open the valve for low pressure side in the manifold gauge to recharge the remaining refrigerant .
4 . After completing, close the valves in manifold gauge and eliminate the hoses from Charging Ports .
Manifold gauge
Low pressure side
Scale
Important information regulation regarding the refrigerant used
• Inform user if system contains 3 kg or more of fluorinated greenhouse gases . In this case, it has to be checked
for leakage at least once every 12 months, according to regulation n°842/2006 . This activity has to be covered by
CAUTION
qualified personnel only . In case situation above (3 kg or more of R-32), installer (or recognised person which has
responsability for final check) has to provide a maintenance book, with all the information recorded according to
REGULATION(EC) N° 842/2006 OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL of 17 May 2006 on certain
fluorinated greenhouse gases .
• For the product that uses the R-32 refrigerant, be cautious not to generate a spark by keeping the following
requirements:
CAUTION
- Do not remove the fuses with power on .
- Do not disconnect the power plug from the wall outlet with power on .
- It is recommended to locate the outlet in a high position . Place the cords so that they are not tangled .
Precautions on adding the R-32 refrigerant
In addition to the conventional charging procedure, . the following requirements shall be kept .
f Make sure that contamination by other refrigerants does not occur for charging .
f
f To minimize the amount of refrigerant, keep the hoses and lines as short as possible .
f
f The cylinders shall be kept upright .
f
f Make sure that the refrigeration system is earthed before charging .
f
f Label the system after charging, if necessary .
f
f Extreme care is required not to overcharge the system .
f
f Before recharging, the pressure shall be checked with nitrogen blowing .
f
f After charging, check for leakage before commissioning .
f
f Be sure to check for leakage before leaving the work area .
f
High pressure side
High pressure side
ENGLISH-43
Low pressure side
Charging port