Screen Innovations Zero Edge / Fixed Installation Instructions Manual

Advertisement

Quick Links

Zero Edge / Fixed
Installation Instructions
INSTALLERS: PLEASE LEAVE THIS MANUAL WITH THE OWNER.
400025
|
v. 2.0 | July 2023

Advertisement

Table of Contents
loading

Summary of Contents for Screen Innovations Zero Edge / Fixed

  • Page 1 Zero Edge / Fixed Installation Instructions INSTALLERS: PLEASE LEAVE THIS MANUAL WITH THE OWNER. 400025 v. 2.0 | July 2023...
  • Page 2 SUGGESTED PROJECTOR PLACEMENT Please visit our Screen Material Wizard (screeninnovations.com/tools/screen-material- wizard/) for the minimum throw distance requirements based on screen material. NOTE: Illustration below shows where the projector should be mounted when using Black Diamond or Slate materials. Better 11° Best 11°...
  • Page 3: Table Of Contents

    TABLE OF CONTENTS Determine Frame Type Standard - Inner Frame Assembly 5 - 6 Split - Inner Frame Assembly 7 - 9 LED Lights Attachment 10 - 11 Determine Your Material Material Attachment Sequence – All Materials Material Rolling Black Diamond & Short Throw Material Only Slate, Pure Material Attachment Maestro 2 (White) –...
  • Page 4: Determine Frame Type

    DETERMINE FRAME TYPE Determine the frame type ordered. If the frame is 120” and above it will be Split frame assembly, anything below 120” will be standard frame assembly. Standard Frame Split Frame...
  • Page 5: Standard - Inner Frame Assembly

    STANDARD - INNER FRAME ASSEMBLY Wear gloves first, clean up and put the PEP foam on the floor. Lay out all innerframe in order on PEP foam to ensure you have all the required pieces. NOTE: Look for the SI logo or a hole for the LED kit lighting (if ordered), that should be the bottom horizontal frame.
  • Page 6 STANDARD - INNER FRAME ASSEMBLY Make sure to patiently adjust the inner frame corner in 90 degree and now secure the screws. It is a critical step to square the frame. Refer to the illustration below. Measure the diagonals to check if the frame is square. If one diagonal is longer, push on the corners at that diagonal. Tighten all set screws once the diagonals are equal or within 1/8’’.
  • Page 7: Split - Inner Frame Assembly

    SPLIT - INNER FRAME ASSEMBLY Wear gloves first, clean up and put the Prep Paper on the floor. Make sure to remove the Vertical support bar and keep it aside safely. Lay out all innerframe in order on Prep Paper to ensure you have all the required pieces.
  • Page 8 SPLIT - INNER FRAME ASSEMBLY Make sure to patiently adjust the inner frame corner in 90 degree and now secure the screws. It is a critical step to square the frame. Refer to the illustration below. Measure the diagonals to check if the frame is square. If one diagonal is longer, push on the corners at that diagonal. Tighten all set screws once the diagonals are equal or within 1/8’’.
  • Page 9 SPLIT - INNER FRAME ASSEMBLY Attach the Vertical support bar, by using the link plates on both sides of vertical support bar and fasten them with the screws to secure it in place. Note: Our Mounting plate can be adjusted to the left or right when mounting the vertical support bar to accomodate a center channel behind the screen when using acoustically transparent material.
  • Page 10: Led Lights Attachment

    LED LIGHTS ATTACHMENT If IP (Zigbee)-controlled LED lights are ordered, Phillips Hue Hub must be purchased and set up separately. Scan the OR code to see the instructions for setup. Connect the LED Controller to the nuts in the frame piece with the screws included. LED Controller hole for feeding wire Feed the wires through the hole.
  • Page 11 LED LIGHTS ATTACHMENT Note: Use caution in the next steps; do not kink or fold the light strip, which will cause damage in the circuit. Use the foam strips provided to losely wrap LEDs around the corners. Press the lights into the channel on the frame. LED foam must be used when rounding the corners to protect the circuit.
  • Page 12: Determine Your Material

    DETERMINE YOUR MATERIAL Non – AT Material (Slate, Pure, Short Throw) Refer to page 13 Maestro 2 – White AT Material Refer to page 14 - 15 PVC – AT Material (Slate AT, Pure AT) Refer to page 15 MATERIAL ATTACHMENT SEQUENCE – ALL MATERIALS Attach the snap attachments in the sequence, as shown.
  • Page 13 SLATE, PURE, SHORT THROW MATERIAL ATTACHMENT Note: Wear gloves when handling material. Carefully unroll the screen material onto a clean floor. Take care to not bend or crease the screen material. Carefully lay the frame onto the screen material. Center the frame over the screen material. Remove and discard the retaining bumpers;...
  • Page 14 MAESTRO 2 – AT MATERIAL (WITH BLACK BACKER) – ATTACHMENT Note: Wear gloves when handling the material. Carefully unroll the screen material onto a clean floor. Take care to not bend or crease the screen material. Unroll the Meastro 2 screen material on the Prep Paper (Refer to instructions on page 12). Flatten any creases and then lay the Black Backer material well aligned over the Maestro 2 material.
  • Page 15: Pvc At Material Attachment

    MAESTRO 2 – AT MATERIAL (WITH BLACK BACKER) – ATTACHMENT Make sure the screen material is centered around the frame before proceeding. If its not centred it could pull on one side damaging the material. Pull the holes in the material and place around the post. Repeat for all four corners and refer to the attachment sequence image on page 12.
  • Page 16: Trim Attachment (Zero Edge And Fixed Frame Trim)

    TRIM ATTACHMENT Attach the vertical trim first onto the screen as shown below. Note: Trim for Fixed screen will be 2” thick, v/s the Zero Edge will be 0.5”.
  • Page 17 TRIM ATTACHMENT Set the horizontal trim with corner brackets; square the corners and tighten corner brackets Fasten the screw to the frame channel. Align the holes in the channel and install screws. Split Frame Only: Connect the horizontals at the middle by installing quantity 4 1/4–20 x 1/4’’ screws trough the trim into the splice bar.
  • Page 18: Wall Mounting

    WALL MOUNTING Install brackets into the wall structure, at least 6” from the edge of the screen and up to 1/3 the width of the screen. Note: Screens above 133” in diagonal with come with 3 brackets. Note: Drill the holes to a firm stud; use a stud finder to locate the studs. TOP OF VIEWING LEVEL "...
  • Page 19: Flown Mounting

    FLOWN MOUNTING Install brackets into wall structure at least 6” from the edge of the screen, up to 1/3 the width of the screen. Screw in through the flown brackets provided, as shown in the image below. Note: Make sure to drill the holes into a beam that can support the weight of the screen. Note: If pulled too far, the screen can be lowered by pushing down on the top of the flying mount.
  • Page 20: Ir Lighting Hex Codes

    IR LIGHTING HEX CODES (TO USE FOR DIFFERENT RE- MOTE CONTROL - REF THE CODES BELOW)
  • Page 21: Ip (Zigbee) Controlled Lighting Setup

    IP (ZIGBEE) CONTROLLED LIGHTING SETUP CONNECT TO LED STRIP Controller input voltage must be in accordance with the required voltage of LED strips. Input voltage = Output Voltage Connect to RGB LED strip diagram MOUNTING Free screw when connecting to LED strip ZIGBEE 3.0 APP CONTROL INSTRUCTION Scan this QR code refer to page 2, to get more details.
  • Page 23 NOTES Notes...