Start Up

Standard Economizer Start-Up

1. Set the minimum position setpoint for the
economizer to the required percentage of minimum
ventilation using the setpoint potentiometer located
on the Economizer Control (ECA).
The economizer will drive to its minimum position
setpoint, exhaust fans (if applicable) may start at
random, and the supply fan will start when the
SERVICE TEST is initiated.
The Exhaust Fan will start anytime the economizer
damper position is equal to or greater than the
exhaust fan setpoint.
2. Verify that the dampers stroked to the minimum
position.
3. Verify that the dampers stroked to the full open
position.
4. To stop the SERVICE TEST, turn the main power
disconnect switch to the "Off" position or proceed
to the next component start-up procedure. Remove
electro mechanical test mode connections (if
applicable).

LLE Controls Test Procedure

See unit schematic for correct wire numbers.
Use the CHECKOUT menu in the Installation
Instructions to test the damper operation and any
configured outputs. Only items that are configured are
shown in the Checkout menu.
To Perform Checkout Tests:
1. Scroll to the desired test in the checkout menu
using the
and
buttons.
2. Press the
button to select the item.
3. "RUN?" is displayed.
4. Press
to start the test.
5. The unit pauses and then displays "IN PROGRESS".
6. When the test is complete, "DONE" appears.
7. When all parameters have been tested, press
(Menu Up) to end the test (e.g. turn off the relay).
24
N N o o t t e e s s : :
The checkout tests can all be performed at
the time of installation or any time during
the operation of the system.
JADE will be in "set up" mode for the first 60
minutes after powered. If OA sensor or Sylk
Bus device (sensor or actuator) is
disconnected during the set up mode, the
JADE will not alarm that failure. The MA
sensor is a system "critical" sensor, if the
MA sensor is removed during the set up
mode, the JADE will alarm. After 60 minutes
the JADE controller will change to operation
mode and all components removed or failed
will alarm in the operation mode.
Upon power up (or after a power outage or
brownout), the JADE controller module
begins a 5 minute power up delay before
enabling mechanical cooling.

Compressor Start-Up

1. Attach a set of service gauges onto the suction and
discharge gauge ports for each circuit. Refer to the
refrigerant circuit illustration in the Service Facts.
Using the Service Test Guide, perform the proper
test mode connections.
S S c c r r o o l l l l C C o o m m p p r r e e s s s s o o r r s s
a. Once each compressor has started, verify that
the rotation is correct. If wired correctly the
suction pressure should drop and the discharge
pressure should rise. If a scroll compressor is
rotating backwards, it will not pump and a loud
rattling sound can be observed.
b. If the electrical phasing is correct, before
condemning a compressor, interchange any two
leads (at the compressor Terminal block) to
check the internal phasing. Refer to the
following illustration for the compressor
terminal/phase identification. Do not allow the
compressor to operate backwards for more than
5 seconds. Operation for a period of time longer
than this will result in compressor damage.
N N o o t t e e : : Copeland SXA scroll compressors for
R410A units use Trane OIL00094.
Compressor types and appropriate oil
charge is listed in the following tables.
RT-SVX057F-EN

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Eb 048 seriesEb 060 seriesEbc036Ebc060Ebc036 seriesEbc048 series ... Show all

Table of Contents