MOUNTING AND CONNECTING THE BURNER

Packing

The burners are despatched in wooden crates whose dimensions are:
series 9x:1730mm x 1280mm x 1020mm (L x P x H)
series 5xx:1730mm x 1430mm x 1130mm (L x P x H)
Packing cases of this type are affected by humidity and are not suitable for stacking.
The following are placed in each packing case:
burner with gas train;
ceramic fibre plait to be inserted between the burner and the boiler;
envelope containing this manual.
To get rid of the burner's packing, follow the procedures laid down by current laws on
disposal of materials.

Handling the burner

ATTENTION! The lhandling operations must be carried out by specialised and trained personnel. If these opera-
tions are not carried out correctly, the residual risk for the burner to overturn and fall down still persists.
To move the burner, use means suitable to support its weight (see paragraph "Technical specifications").
The unpacked burner must be lifted and moved only by means of a fork lift truck.
The burner is mounted on a stirrup provided for handling the burner by means of a fork lift truck: the forks must be inserted into the A
anb B ways. Remove the stirrup only once the burner is installed to the boiler.

Fitting the burner to the boiler

To install the burner into the boiler, proceed as follows:
1
make a hole on the closing door of the combustion chamber as described on paragraph "Overall dimensions")
2
place the burner to the boiler: lift it up and handle it according to the procedure described on paragraph "Handling the burner";
3
place the 4 stud bolts (5), according to the burner's drilling plate described on paragraph "Overall dimensions";
4
fasten the 4 stud bolts;
5
place the ceramic fibre plait on the burner flange;
6
install the burner into the boiler;
7
fix the burner to the stud bolts, by means of the fixing nuts, according to the next picture.
8
After fitting the burner to the boiler, ensure that the gap between the blast tube and the refractory lining is sealed with appropriate
insulating material (ceramic fibre cord or refractory cement).
The burner is designed to work positioned according to the picture below. For different installations, please contact the Technical
Department.
H
A
Keys
1
Burner
2
Fixing nut
3
Washer
4
Ceramic fibre plait
5
Stud bolt
7
Blast tube
13
L
P
B

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rx91Rx510Rx515Rx520

Table of Contents