Test Run; Preparing For Test Run - Sanyo CHDZ07263 Service Manual

Hide thumbs Also See for CHDZ07263:
Table of Contents

Advertisement

1. Test Run

1-1. Preparing for Test Run

Before attempting to start the air conditioner, check the fol-
lowing.
(1) All loose matter is removed from the cabinet, especially
steel fi lings, bits of wire, and clips.
(2) The control wiring is correctly connected and all electrical
connections are tight.
(3) The protective spacers for the compressor used for trans-
portation have been removed. If not, remove them now.
(4) The transportation pads for the indoor fan have been
removed. If not, remove them now.
(5) The power has been connected to the unit for at least 5
hours before starting the compressor. The bottom of the
compressor should be warm to the touch and the crank-
case heater around the feet of the compressor should be
hot to the touch.
(6) Both the gas and liquid tube service valves are open. If
not, open them now.
(7) Request that the customer be present for the trial run.
Explain the contents of the instruction manual, then have
1
the customer actually operate the system.
(8) Be sure to give the instruction manual and warranty cer-
tifi cate to the customer.
(9) When replacing the control PCB, be sure to make all the
same settings on the new PCB as were in use before
replacement.
2
The existing EEP ROM is not changed, and is connected
to the new control PCB.
3
4
5
6
7
Power mains switch
Balance tube
Liquid tube
Discharge tube
1 - 2
Test Run
ON
(Power must be turned ON
at least 5 hours before
attempting test run)
Suction tube

Advertisement

Table of Contents
loading

Table of Contents