5.2 Install the main body
C
1
Installing Ø10 hanging screw bolts. (4 bolts)
Please Refer to Fig.5-3 and Fig.5-4 for the hanging screw
bolts distance
Evaluate the ceiling construction and please install with
hanging screw bolts.
The handling to the ceiling varies from the constructions,
consult the construction person for the specific condition.
Do keep the ceiling flat. Consolidate the roof beam
possible vibration.
Cut off the roof beam.
Strengthen the place that has been cut off, and
consolidatethe roof beam.
After the selection of installation location, position the refrigerant
pipes, drain pipes,indoor & outdoor wires to the connection
places before hanging up the machine.
The installation of hanging screw bolts.
WOODEN CONSTRUCTION
Put the square timber traversely overthe roof beam, then install
the hanging screw bolts.
Timber over the beam
Hanging screw bolts
installation manual
4
D. Connecting point of
refrigerant pipe
(D. gas side)
Drain point
E. Connecting point of
refrigerant pipe
(E. Liquid side)
D
Hook
Fig. 5-2
10
Ø
to avoid
Roof beam
Ceiling
Fig.5-3
NEW CONCRETE BRICKS
Inlaying or embedding the screw bolts.
(Blade shape
insertion)
Steel bar
Embedding screw bolt
(Pipe hanging and embedding screw bolt)
FOR ORIGINAL CONCRETE BRICKS
Install the hanging hook with expansible bolt into the concrete
deep to 45~50mm to prevent loose.
STEEL ROOF BEAM STRUCTRUE
Install and use directly the supporting angle steel.
Hanging screw bolt
Hanging
bolts
Fig.5-7
2
Install the indoor unit.
Remove the side board and the grille. (Refer to Fig. 5-8)
Hanging arm
H a n g i n g
s c r e w b o l t
Grille
(Slide insertion)
Fig.5-4
Fig.5-5
Fig.5-6
Supporting
angle steel
Fig.5-7
Side board
Fig.5-8