Chapter 4 Installation Prerequisites; Pre-Start Checks; Torque Information - DANIEL V707 User Manual

Spring loaded back pressure valve nps 2 through 4 / class 150-600
Hide thumbs Also See for V707:
Table of Contents

Advertisement

SPRING LOADED BACK PRESSURE VALVE
User manual
DAN-20064957
4
4.1
4.2
User manual
30
www.Daniel.com
Installation prerequisites

Pre-start checks

Ensure that the pipeline is completely free of all foreign material before installing the
valve. The design of the control valve has not been assessed for the effects of traffic, wind
or earthquake loading. Provide fire prevention measures and equipment per local
regulations.

Torque information

NOTICE
When installing the control valve, ensure that the bolts conform to the requirements of
ASME B16.5 paragraph 5.3 and to the material requirements of ASME B16.5 Table 1B.
Gaskets must conform to the requirements of ASME B16.20.
Tightening procedure:
1. Lubricate the nuts and bolts.
2. Hand-tighten until the nuts and bolts are snug against the flanges.
3. Use the minimum pressure setting on an air wrench.
4. Use the correct tightening sequence for the bolt flanges.
5. Follow your company's internal flange installation procedures.
Important
Ensure that piping or other attachments connected to the control valve are not under
stress.
Important
Provide fire prevention measures and equipment per local regulations.
Flanges with 4 and 8 bolts
First round - 30% of final torque (flange sequential order)
Second round- 60% of final torque (flange sequential order)
Third round - 100% of final torque (flange sequential order)
One final time - clockwise or counter clockwise sequentially around the flange
Installation prerequisites
August 2019
37