Installation Guidelines
• Where a wall or other obstacle is in the path of outdoor unit's intake or exhaust airflow, follow the installation guidelines below.
• For any of the below installation patterns, the wall height on the exhaust side should be 1200mm or less.
Wall facing one side
More than 100
Walls facing three sides
More than 50
Top view

Precautions on Installation

• Check the strength and level of the installation ground so that the unit will not cause any operating vibration or noise after installed.
• In accordance with the foundation drawing, fix the unit securely by means of the foundation bolts. (Prepare four sets of M8 or M10
foundation bolts, nuts and washers each which are available on the market.)
• It is best to screw in the foundation bolts until their length are 20mm from the foundation surface.

Outdoor Unit Installation

1.
Installing Outdoor Unit
1) When installing the outdoor unit, refer to "Precautions for Selecting the Location" and the "Outdoor Unit Installation Drawings".
2) If drain work is necessary, follow the procedures below.
2.
Drain Work
1) Use drain plug for drainage.
2) If the drain port is covered by a mounting base or floor surface, place addi-
tional foot bases of at least 30mm in height under the outdoor unit's feet.
3) In cold areas, do not use a drain hose with the outdoor unit.
(Otherwise, drain water may freeze, impairing heating performance.)
■English
More than 350
1200
or less
Side view
More than 100
More than 350
Unit: mm
Walls facing two sides
More than 350
More
than 100
More than 50
Top view
More than 50
Drain-water hole
Bottom frame
Drain plug
Hose (available commercially,
inner dia. 16mm)
4