5 Installation
4 Do the following:
▪ Connect the liquid pipe (a) to the liquid stop valve. (brazing)
▪ Connect the gas pipe (b) to the gas stop valve. (brazing)
b
a
NOTICE
When brazing: First braze the liquid side piping, then the
gas side piping. Enter the electrode from the front of the
unit and the welding torch from the right side to braze with
the flames facing outside and avoid the compressor sound
insulation and other piping.
A
a
b
a Electrode
b Burning-resistant plate
c Welding torch
d Flames
e Compressor sound insulation
f Liquid side piping
g Gas side piping
▪ Connect the gas piping accessories (c, d), and cut them to
the required length (d1).
Possibility 1: To the front
d1
d
c
Possibility 3: To the side
c d d1
5 Reattach the service cover and the piping intake plate.
Installation and operation manual
10
A
e
d
c
a
b f
g
c
Possibility 2: To the back
c
d
Possibility 4: Downwards
d
d1
6 Seal all gaps (example: a) to prevent snow and small animals
from entering the system.
a
WARNING
Provide adequate measures to prevent that the unit can be
used as a shelter by small animals. Small animals that
make contact with electrical parts can cause malfunctions,
smoke or fire.
NOTICE
Make sure to open the stop valves after installing the
refrigerant piping and performing vacuum drying. Running
the system with the stop valves closed may break the
compressor.
5.4

Checking the refrigerant piping

5.4.1

About checking the refrigerant piping

Refrigerant piping works are
finished?
No
Yes
The indoor units and/or
outdoor unit were already
No
powered ON?
Yes
Use procedure:
"Method 2: After power ON".
It is very important that all refrigerant piping work is done before the
units (outdoor or indoor) are powered on.
When the units are powered on, the expansion valves will initialise.
This means that they will close. Leak test and vacuum drying of field
piping and indoor units is impossible when this happens.
Therefore, there will be explained 2 methods for initial installation,
leak test and vacuum drying.
Method 1: Before power ON
If the system has not yet been powered on, no special action is
required to perform the leak test and the vacuum drying.
Method 2: After power ON
If the system has already been powered on, activate setting [2‑21]
(refer to
"6.1.4  To access mode 1 or 2"  on page 
will open field expansion valves to guarantee a R410A piping
pathway and make it possible to perform the leak test and the
vacuum drying.
NOTICE
Make sure that all indoor units connected to the outdoor
unit are powered on.
NOTICE
Wait until the outdoor unit has finished the initialisation to
apply setting [2‑21].
Finish piping work.
Use procedure:
"Method 1: Before power ON
(regular method)".
16). This setting
RXYSQ6TMYFK
VRV IV-S system air conditioner
4P524881-1 – 2018.02

Advertisement

Table of Contents
loading

Table of Contents