Packing List

LP (Propane) Conversion Kit:
Thimble (2-Piece Assembly)
Pipe Shield, Header Shield (shipped attached to the top of
fireplace)
Wall Switch, Cover Plate, and Wire

Additional Items Required

Gas Line Equipment (shutoff valve, pipe, etc.)
Electrical Equipment (min. 14 gauge, grounded line)
The 42PB Requires 5 lbs. of 1/4" Crushed Glass
The 54PB Requires 6 lbs. of 1/4" Crushed Glass
94500580 Platinum (10 lbs.)
94500581 Bronze (10 lbs.)
94500582 Cobalt (10 lbs.)
94500583 Black (10 lbs.)

Recommended Installation Procedure

Frame the opening for the fireplace. Make sure to allow for vent installation.
Install the vent, gas line, and electrical hook-up.
Install the drywall.
Install the hearth (if applicable).
Install the facing (if applicable).
Install the mantel (if applicable).
Install fireback (optional).
Install logs (optional) and glass media.
Finalize the installation (see page 51).
© Travis Industries
Installation
(for qualified installers only)
(42PB) Burner Orifice (1.45mm), Pilot Orifice (0.14 LP), LP Regulator
(54PB) Burner Orifice (1.65mm), Pilot Orifice (0.14 LP), LP Regulator
4/19/23 - 1453
PB 42 & 54 MV/GSB2/GSR2 Install
9