5. Set concrete
a. Reference the options below and pour concrete to the top edge of the frame,
leveling to finish flush with the top flange of the floor door. Allow to cure for
seven days prior to opening the floor door. Opening the unit prior may crack
the concrete.
b. After the seven days for concrete curing, open the door(s)
and inspect the unit for excess concrete that may have
seeped or fallen into the hinges, or latch. (The doors will be
heavy until the springs are engaged; opening will require
two people.) It is important to note that springs will be
disengaged on doors with more than two springs. Remove
any concrete to ensure smooth operation.
6. Engage Springs
a. Manually open the door to the 90-degree position. The hold open
b. While in the 90-degree position the spring should settle on the plate at the
c. Slide in the keeper extension until it rests on the spring. (Figure 1)
d. Slide the spring keeper down until it touches the top of the spring keeper
e. Disengage the hold open arm to test the closing and opening operation. If
7.
Adjust Spring (optional)
Note: Spring position is factory set. Adjust only if field conditions
require more or less spring force.
a. Open the door to the 90-degree position, the hold open
arm will automatically hold the door open.
b. First, disengage the spring by loosening the two hex head screws in the spring
keeper. (Figure 2)
Great Products. Better Partners.
Babcock-Davis is a leader in roof hatches, smoke vents and safety railings for the commercial roofing market. We also
manufacture architectural access and safety-related building products for commercial structures. Babcock-Davis provides
local connections through a broad distribution network to accelerate and simplify the building process for contractors and
building owners, offering hassle-free services including access to technical experts, REVIT tools for BIM, HPDs for LEED v4, 3-
part specifications and AIA-accredited continuing education courses.
courses.
arm, will automatically hold the door open.
bottom of the housing.
extension. Using a ½-inch wrench tighten the two hex head screws.
the door does not close fully, slide the keeper back away from the keeper
extension and retighten.
Installation & Operation + Maintenance
FIRE-RATED FLOOR DOORS
Model: BFDF
©2021 Babcock-Davis
Figure 1
Figure 2
5
Rev 07/2021

Advertisement

Table of Contents
loading

Related Products for babcockdavis BFDF

Table of Contents